TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/MIN/46859/2020              (ii). Name of Project for which Forest Land is required : Collection of minor mineral from Chandrabhaga River, Narendranagar Forest Division              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : In due course of time heavy deposition of RBM in river bed of this river has taken place. This heavy deposion of RBM causes heavy flood during rainy season which erodes the banks of river and causes heavy damage to adjoining forest lands. By extracting RBM from the river bed flooding can be prevente              (iv). File no. : 8-18/2020-FC              (v). State : Uttarakhand              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 190
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onStage-II Approval on
FP/UK/MIN/46859/202027/06/202029/06/2020   08/07/2020   16/07/2020   18/07/2020 Narendranagar,Munikireti :18/07/2020Bhagirathi:
  29/07/2020 (Narendranagar,Munikireti)

Uttarakhand:
07/08/2020
Uttarakhand:
12/08/2020
01/09/202002/03/2021
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 29/09/2020  
Replied by State Government (Uttarakhand) on:17/12/2020  
Query raised by State Government (Uttarakhand) on:02/10/2020  
Replied by Nodal Officer (Uttarakhand) on:17/12/2020  
Query raised by Nodal Officer (Uttarakhand) on:02/10/2020  
Replied by Circle(Bhagirathi) on:25/11/2020  
Query raised by Nodal Officer (Uttarakhand) on:27/11/2020  
Replied by Circle(Bhagirathi) on:15/12/2020  
Query raised by Circle (Bhagirathi) on:03/10/2020  
Replied by DFO (Narendranagar,Munikireti) on:23/11/2020  
Query raised by Circle (Bhagirathi) on:27/11/2020  
Replied by DFO (Narendranagar,Munikireti) on:27/11/2020  
Query raised by Circle (Bhagirathi) on:27/11/2020  
Replied by DFO (Narendranagar,Munikireti) on:14/12/2020  
Query raised by DFO (Narendranagar,Munikireti) on:06/10/2020  
Replied by UA on :11/11/2020  
Query raised by DFO (Narendranagar,Munikireti) on:27/11/2020  
Replied by UA on :08/12/2020  
NOTE:- Stage-I Approval accorded by : Head Office .