TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TN/TRANS/155570/2022              (ii). Name of Project for which Forest Land is required : Erection of 110 KV Transmission line from Rayakottai – Kelamangalam road to TATA Electronics Company in S.F. Nos. 954-956, 959-965, 970-972, 977 & 978 (Part-1), (Part-2) and (Part-3) of Ayaranapalli P              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Erection of 110 KV Transmission line from Rayakottai – Kelamangalam road to TATA Electronics Company in S.F. Nos. 954-956, 959-965, 970-972, 977 & 978 (Part-1) (0.21.12), (Part-2) (0.11.44) (Part-3) (0.66.00) to an extent of 0.98.56 ha of Ayaranapalli Panchayat, Shoolagiri Taluk, which is mentioned              (iv). File no. : 4-TNB102/2023-CHN              (v). State : Tamil Nadu              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.9856
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/TN/TRANS/155570/202219/05/202229/06/2022   01/07/2022   15/07/2022   12/08/2022 Hosur :27/08/2022Dharmapuri:
  20/09/2022 (Hosur)

Tamil Nadu:
12/10/2022
Tamil Nadu:
12/12/2022
Chennai:
25/04/2023
11/05/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Tamil Nadu) on:03/01/2023  
Replied by Nodal Officer (Tamil Nadu) on:13/02/2023  
Query raised by Nodal Officer (Tamil Nadu) on:18/10/2022  
Replied by Circle(Dharmapuri) on:29/10/2022  
Query raised by Nodal Officer (Tamil Nadu) on:10/11/2022  
Replied by Circle(Dharmapuri) on:24/11/2022  
Query raised by Nodal Officer (Tamil Nadu) on:04/01/2023  
Replied by Circle(Dharmapuri) on:07/02/2023  
Query raised by Circle (Dharmapuri) on:20/10/2022  
Replied by DFO (Hosur) on:28/10/2022  
Query raised by Circle (Dharmapuri) on:10/11/2022  
Replied by DFO (Hosur) on:24/11/2022  
Query raised by Circle (Dharmapuri) on:05/01/2023  
Replied by DFO (Hosur) on:02/02/2023  
Query raised by Circle (Dharmapuri) on:06/02/2023  
Replied by DFO (Hosur) on:06/02/2023  
Query raised by DFO (Hosur) on:17/09/2022  
Replied by UA on :19/09/2022  
Query raised by DFO (Hosur) on:14/11/2022  
Replied by UA on :23/11/2022  
Query raised by DFO (Hosur) on:05/01/2023  
Replied by UA on :25/01/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .