Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Trichy)
|
03/11/2015
|
As instructed during monthly meeting the CF is requested to upload the Certificates/Undertakings furnished by the User Agency as additional documents
|
|
2
|
CF (Trichy)
|
EDS
|
DFO (Nagapattinam WL)
|
19/11/2015
|
The DFO is requested to upload the certificates/Undertakings furnished by the User Agency as additional documents
|
|
3
|
DFO (Nagapattinam WL)
|
EDS
|
User Agency (tndehnagai@gmail.com)
|
20/11/2015
|
The User Agency is requested to upload the certificates/ Undertakings as additional documents for further processing.
|
|
4
|
User Agency (tndehnagai@gmail.com)
|
REPLY
|
DFO (Nagapattinam WL)
|
01/12/2015
|
Certificate of undertakings for additional amount, compensatory afforestation, minimum forest involvement, alternative non forest land available, non scheduled tribe, project details, drawings,Certificate of District collector, Nagapattinam.
|
|
5
|
DFO (Nagapattinam WL)
|
EDS
|
User Agency (tndehnagai@gmail.com)
|
22/12/2015
|
The user agency is requested to upload the undertaking certificate to pay for Net present value immeidately
|
|
6
|
User Agency (tndehnagai@gmail.com)
|
REPLY
|
DFO (Nagapattinam WL)
|
16/03/2016
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Nagapattinam WL)
|
EDS
|
User Agency (tndehnagai@gmail.com)
|
23/08/2016
|
The user agency is requested to upload certificates/undertakings as additional documents for further processing
|
|
8
|
User Agency (tndehnagai@gmail.com)
|
REPLY
|
DFO (Nagapattinam WL)
|
24/08/2016
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Nagapattinam WL)
|
REPLY
|
CF (Trichy)
|
30/08/2016
|
The User Agency has uploaded all the Certificates and Undertakings as additional documents.
|
|
10
|
CF (Trichy)
|
REPLY
|
Nodal Officer
|
01/09/2016
|
The Certificates and Undertakings sought as EDS by the Nodal Officer has been uploaded by the User Agency.
|
|