Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Madurai)
|
11/03/2020
|
The APCCF is requested to upload the Part III of proposal.
|
|
2
|
CF (Madurai)
|
REPLY
|
Nodal Officer
|
12/03/2020
|
Part III uploaded for Theni Byepass Road as per request
|
|
3
|
State secretary
|
EDS
|
Nodal Officer
|
03/08/2020
|
Kindly furnish the details vide Govt lr 6353 2020 dated 28.05.2020
|
|
4
|
Nodal Officer
|
REPLY
|
State secretary
|
03/08/2020
|
The details furnished along with enclosures is enlcoded.
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
22/12/2020
|
As per EDS
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
01/03/2021
|
Nodal Officer is requested clarify the details vide Govt letter dt. 31.12.2020 for further action.
|
|
7
|
Nodal Officer
|
REPLY
|
State secretary
|
01/03/2021
|
EDS query solved vide PCCF ref No. 39100 dt 18.02.2021
|
|
8
|
State secretary
|
EDS
|
Nodal Officer
|
03/09/2021
|
Nodal Officer is requested to upload the details vide Govt letter for further action.
|
|
9
|
Nodal Officer
|
REPLY
|
State secretary
|
03/09/2021
|
Reply to EDS query uploaded
|
|
10
|
State secretary
|
REPLY
|
Regional Office
|
07/09/2021
|
EDS query solved
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
04/10/2021
|
As per attached EDS
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
20/11/2021
|
Nodal Officer is requested to rectify the the details vide Govt of India letter for further action.
|
|
13
|
Nodal Officer
|
EDS
|
CF (Madurai)
|
20/11/2021
|
The Circle Officer is requested to rectify the defects pointed out by the GOI letter dt 04.10.2021 for further process.
|
|
14
|
CF (Madurai)
|
EDS
|
DFO (Theni)
|
20/11/2021
|
Further details sought for
|
|
15
|
DFO (Theni)
|
EDS
|
User Agency (tndehtheni@gmail.com)
|
01/12/2021
|
Further details sought for
|
|
16
|
User Agency (tndehtheni@gmail.com)
|
REPLY
|
DFO (Theni)
|
13/12/2021
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Theni)
|
EDS
|
User Agency (tndehtheni@gmail.com)
|
13/12/2021
|
The User Agency is requested to update the part-I of the proposal as per the reduced area.
|
|
18
|
User Agency (tndehtheni@gmail.com)
|
REPLY
|
DFO (Theni)
|
22/12/2021
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Theni)
|
EDS
|
User Agency (tndehtheni@gmail.com)
|
23/12/2021
|
User Agency is requested to comply the Condition Ref. b as per the GOI letter Ref. F.No.4-TNB068/2020-CHN/942 dated 04.10.2021
|
|
20
|
User Agency (tndehtheni@gmail.com)
|
REPLY
|
DFO (Theni)
|
04/04/2022
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Theni)
|
EDS
|
User Agency (tndehtheni@gmail.com)
|
26/04/2022
|
User Agency is requested to confirm that any trees to be felled due to this widening of By Pass Road Project.
|
|
22
|
User Agency (tndehtheni@gmail.com)
|
REPLY
|
DFO (Theni)
|
26/04/2022
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Theni)
|
REPLY
|
CF (Madurai)
|
28/04/2022
|
Sir,
I submit that the following documents listed below are enclosed herewith for kind perusal,
1) Site Inspection Report & Photographs
2) Recommendation Report
3) Hard Copy of the revised Proposal received from the User Agency
(3 Copies)
4) Part – II of the proposal (3 copies)
5) Estimate for the Compensation Afforestation.
This is for favour of kind information.
|
|
24
|
CF (Madurai)
|
REPLY
|
Nodal Officer
|
05/05/2022
|
Sir, I submit that the revised proposal as called for by the Government has been submitted and the connected documents for this diversion proposal has already been uploaded by the District Forest Officer, Theni.
|
|
25
|
Nodal Officer
|
EDS
|
CF (Madurai)
|
24/05/2022
|
The Circle level Officer and the DFO are requested to upload the revised CA scheme as per GOI guidelines and upload the revised Part II for further process
|
|
26
|
CF (Madurai)
|
EDS
|
DFO (Theni)
|
26/05/2022
|
Addtional details called by the Pccf
|
|
27
|
DFO (Theni)
|
REPLY
|
CF (Madurai)
|
26/05/2022
|
Sir,
I submit that the Revised CA Amount is enclosed herewith.
|
|
28
|
CF (Madurai)
|
REPLY
|
Nodal Officer
|
08/06/2022
|
Revised part II and Estimate copy Submission- reg
|
|
29
|
Nodal Officer
|
REPLY
|
State secretary
|
22/06/2022
|
Reply to the EDS query called for by the GOI is furnished and submitted.
|
|
30
|
State secretary
|
REPLY
|
Regional Office
|
22/08/2022
|
Reply to EDS query
|
|