TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TN/ROAD/21451/2016              (ii). Name of Project for which Forest Land is required : Access Road to Sai Leo Quarry and Other Villagers              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : For the proposed widening of existing approved cart track approch road leading to sai leo quarry in nallur RF nearby chennai city,an area of 0.63 Hectares(1.56 Acres)of forest land is required.              (iv). State : Tamil Nadu              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.7044
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/TN/ROAD/21451/201621/03/201703/08/2018  17/07/2018  30/05/2018  28/11/2017  12/05/2017   28/09/2018  28/07/2018  23/06/2018  08/05/2018  28/06/2017   26/10/2018   13/12/2018 Chengalpattu,Kancheepuram :22/01/2019
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Chengalpattu,Kancheepuram) on:29/01/2019  
Replied by UA on :07/02/2019  
Query raised by DFO (Chengalpattu,Kancheepuram) on:02/03/2019  
Replied by UA on :25/03/2019  
Query raised by DFO (Chengalpattu,Kancheepuram) on:04/04/2019  
Replied by UA on :05/07/2019  
Query raised by DFO (Chengalpattu,Kancheepuram) on:22/08/2019  
Replied by UA on :11/10/2019  
Query raised by DFO (Chengalpattu,Kancheepuram) on:14/11/2019  
Replied by UA on :  
NOTE:- Proposal is pending at DELISTED (due to non-reply of EDS by UA within 90 days) due to EDS raised by DELISTED .
Close(X)
Close(X)
Please wait ...