TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TN/ROAD/101799/2020              (ii). Name of Project for which Forest Land is required : Road to Combined Court Complex at Udhagamandalam              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Easy road access to the Combined Court Complex at Udhagamandalam, since there is no approach road to the Court Complex. More than 2000 people i.e:- Judges, Advocates, Advocate clerks, Police, Litigants and Court staff will be visiting the premises per day so the road approach is very vital.              (iv). File no. : 4-TNB086/2022-CHN              (v). State : Tamil Nadu              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.33
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/TN/ROAD/101799/202028/12/202012/02/2021   15/06/2021   29/06/2021   24/08/2021 Nilgiris North :08/09/2021Coimbatore:
  29/10/2021 (Nilgiris North)

Tamil Nadu:
02/11/2021
Tamil Nadu:
11/04/2022
Chennai:
05/05/2022
06/05/2022
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Tamil Nadu) on:03/12/2021  
Replied by Circle(Coimbatore) on:18/03/2022  
Query raised by Circle (Coimbatore) on:17/02/2022  
Replied by DFO (Nilgiris North) on:18/02/2022  
Query raised by DFO (Nilgiris North) on:10/10/2021  
Replied by UA on :22/10/2021  
Query raised by DFO (Nilgiris North) on:17/02/2022  
Replied by UA on :18/02/2022  
NOTE:- Stage-I Approval accorded by : Regional Office .