TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TN/Pipeline/35736/2018              (ii). Name of Project for which Forest Land is required : Desilting open well, Providing 2 No's Bore Well and Laying of Pipeline from open well to Forest Check Post near Varattuppallam Dam in Anthiyur RF of Erode Division Portion of this Pipe Line 1450 m run              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Desilting open well, Providing 2 Nos Bore Well and Laying of Pipe line form open well to Sellampalayam Check Post for the distance of 1010m and 0.60m width, open well 6.30m dia and Two nos bore well (0.0638 hect) in South Bargur RF and Pipeline 900m x 0.60m (0.054 hact) in Ennamangalam RF of Erod              (iv). State : Tamil Nadu              (v). Category of the Project : Pipeline              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.1178
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/TN/Pipeline/35736/201812/09/201826/03/2019  22/01/2019  14/11/2018  25/09/2018   06/05/2019  05/03/2019  04/01/2019  26/10/2018   27/05/2019   28/06/2019 Erode :20/07/2019
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Erode) on:29/08/2019  
NOTE:- Proposal is pending at DELISTED (due to non-reply of EDS by UA within 90 days) due to EDS raised by DELISTED .