TimeLine Details
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
A.
General Details
(i). Proposal No. :
FP/TN/Pipeline/35736/2018
(ii). Name of Project for which Forest Land is required :
Desilting open well, Providing 2 No's Bore Well and Laying of Pipeline from open well to Forest Check Post near Varattuppallam Dam in Anthiyur RF of Erode Division Portion of this Pipe Line 1450 m run
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Desilting open well, Providing 2 Nos Bore Well and Laying of Pipe line form open well to Sellampalayam Check Post for the distance of 1010m and 0.60m width, open well 6.30m dia and Two nos bore well (0.0638 hect) in South Bargur RF and Pipeline 900m x 0.60m (0.054 hact) in Ennamangalam RF of Erod
(iv). State :
Tamil Nadu
(v). Category of the Project :
Pipeline
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Area of forest land proposed for diversion(in ha.):
0.1178
B.
Time Line
Proposal No.
Submitted by User Agency
Query for Shortcoming(if any) by Nodal Officer
Resubmission of Proposal by User Agency
Query by Nodal Officer for submitting Hard Copies
Uploading(by U.A.) of copies of receipt received from DFO & DC
Division
Circle
Nodal Office
State Government
Regional Office
Stage-I Approval on
Stage-II Approval on
FP/TN/Pipeline/35736/2018
12/09/2018
26/03/2019
22/01/2019
14/11/2018
25/09/2018
06/05/2019
05/03/2019
04/01/2019
26/10/2018
27/05/2019
28/06/2019
Erode
:
20/07/2019
C. Essential Details Sought History
 
Communication between Regional Office & State Government
Communication between State Government & Nodal Officer
Communication between Nodal Officer & Circle
Communication between Circle & Division
Communication between Division & User Agency
Query raised by DFO (Erode) on:
29/08/2019
NOTE:-
Proposal is pending at
DELISTED (due to non-reply of EDS by UA within 90 days)
due to EDS raised by
DELISTED
.
Close(X)
Close(X)
Please wait ...
EDS History
×
EDS History
×
Proposal No.-
Sno.
From
Status
To
EDS Date
EDS sought/Replied
EDS Letter
1
DFO (Erode)
EDS
User Agency (anthiyursubdivision@gmail.com)
29/08/2019
The User agency is requested to rectify the defects and upload details
EDS History(Stage-II)
×