Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Vellore)
|
EDS
|
User Agency (balsamy.thirunagalingam@ril.com)
|
04/07/2023
|
The On line proposal submitted by the User Agency ie JIO for diversion of 0.031Ha of Forest land in Pallikonda RF for laying of underground OFC purpose vide reference cited has been verified and the following additional details are required to process the proposal
As per the rule 11 of the Forest Conservation rules 2022 Compensatory afforestation land equivalent to the Forest area to be diverted has to be identified by the user agency and it has to be mutated to the Forest Department. The cost of raising of compensatory afforestation has to be borne by the user agency as such the following details are also required
A KML file of the Compensatory afforestation land
B SI Sheet Map marking the location of the Compensatory afforestation land with
GPS reading
|
|
2
|
User Agency (balsamy.thirunagalingam@ril.com)
|
REPLY
|
DFO (Vellore)
|
11/07/2023
|
The correction have been made as per the instruction received
|
|
3
|
CF (Vellore)
|
EDS
|
DFO (Vellore)
|
18/08/2023
|
Rectified the proposal hard copy not received.
|
|
4
|
DFO (Vellore)
|
REPLY
|
CF (Vellore)
|
29/08/2023
|
the hard copy submitted today
|
|
5
|
CF (Vellore)
|
EDS
|
DFO (Vellore)
|
04/09/2023
|
The District Forest Officer, Vellore is requested to is rectify the shortcomings vide PCCF ref No.TS4/14436/2023 dt.30.08.2023
|
|
6
|
DFO (Vellore)
|
REPLY
|
CF (Vellore)
|
31/10/2023
|
the correction have been made as per the instruction received
|
|
7
|
CF (Vellore)
|
EDS
|
DFO (Vellore)
|
14/11/2023
|
Rectified the proposal hard copy triplicate not received. Remarks on site inspection report has to be furnished
|
|
8
|
DFO (Vellore)
|
REPLY
|
CF (Vellore)
|
08/12/2023
|
The hard copy triplicate submitted
|
|
9
|
CF (Vellore)
|
EDS
|
DFO (Vellore)
|
12/12/2023
|
The DFO is requested to obtain Collector Certificate from the User Agency and Upload the same in the web portal
|
|
10
|
DFO (Vellore)
|
EDS
|
User Agency (balsamy.thirunagalingam@ril.com)
|
20/12/2023
|
The user agency has not furnished the District Collector certificate on non-availability of non-Forest land for the Project.
|
|
11
|
User Agency (balsamy.thirunagalingam@ril.com)
|
REPLY
|
DFO (Vellore)
|
20/12/2023
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Vellore)
|
EDS
|
User Agency (balsamy.thirunagalingam@ril.com)
|
04/06/2024
|
to correct the RF name
|
|