Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Madurai)
|
EDS
|
DFO (Theni)
|
07/06/2021
|
Send hard copy of the proposals
|
|
2
|
DFO (Theni)
|
REPLY
|
CF (Madurai)
|
08/06/2021
|
I submit that the hard copy of the prposal has been submitted vide DFO letter reference C.No. 7126/2016/D dated 08.06.2021.
|
|
3
|
Nodal Officer
|
EDS
|
CF (Madurai)
|
26/11/2021
|
DFO is requested to upload the details vide PCCF ref No.TS4/32117 /2016 dt.22.11.2021.
|
|
4
|
CF (Madurai)
|
EDS
|
DFO (Theni)
|
02/12/2021
|
further details called for
|
|
5
|
DFO (Theni)
|
REPLY
|
CF (Madurai)
|
05/01/2022
|
I submit that the reply for the query's raised by the Principal Chief Conservator of Forests, (HoD), Chennai vide TS4/32117/2016 dated 22.11.2021 is enclosed herewith.
|
|
6
|
CF (Madurai)
|
REPLY
|
Nodal Officer
|
24/01/2022
|
Additional details submission of Reg
|
|
7
|
Regional Office
|
EDS
|
State secretary
|
31/05/2022
|
As per attached EDS
|
|
8
|
State secretary
|
EDS
|
Nodal Officer
|
13/08/2022
|
The details sought from Regional Office, as per attached document, may be replied at once
|
|
9
|
Nodal Officer
|
EDS
|
CF (Madurai)
|
01/09/2022
|
The CF&FD is requested to furnish the details called for by the GOI.
|
|
10
|
CF (Madurai)
|
EDS
|
DFO (Theni)
|
08/09/2022
|
Additional particulars called for
|
|
11
|
DFO (Theni)
|
REPLY
|
CF (Madurai)
|
09/09/2022
|
I submit that the reply for the query has been submitted vide DFO letter C.No. 7126/2016/D dated 25.07.2022 and the same is enclosed herewith.
|
|
12
|
CF (Madurai)
|
REPLY
|
Nodal Officer
|
26/09/2022
|
Additional details submission - Reg.
|
|
13
|
Nodal Officer
|
EDS
|
CF (Madurai)
|
13/10/2022
|
The CF&FD is requested to upload the details vide PCCF ref No.TS4/32117 /2016 dt.10.10.2022.
|
|
14
|
CF (Madurai)
|
EDS
|
DFO (Theni)
|
17/10/2022
|
Further details called for regarding.
|
|
15
|
DFO (Theni)
|
REPLY
|
CF (Madurai)
|
07/12/2022
|
Sir, report submission
|
|
16
|
CF (Madurai)
|
REPLY
|
Nodal Officer
|
19/12/2022
|
Additional details submission of reg.
|
|
17
|
Nodal Officer
|
REPLY
|
State secretary
|
03/02/2023
|
The details called for by the GOI is submitted.
|
|
18
|
State secretary
|
REPLY
|
Regional Office
|
12/07/2024
|
Reply furnishing of -regarding
|
|