Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Cuddalore)
|
EDS
|
User Agency (mohan.ramalingam@stl.tech)
|
09/06/2023
|
kindly submit the 5 Nos of Proposal hot copy
|
|
2
|
User Agency (mohan.ramalingam@stl.tech)
|
REPLY
|
DFO (Cuddalore)
|
13/10/2023
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Cuddalore)
|
EDS
|
User Agency (mohan.ramalingam@stl.tech)
|
17/10/2023
|
till now hot copy not received so, kindly submit the 5 Nos of Proposal hot copy
|
|
4
|
User Agency (mohan.ramalingam@stl.tech)
|
REPLY
|
DFO (Cuddalore)
|
08/12/2023
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Cuddalore)
|
EDS
|
User Agency (mohan.ramalingam@stl.tech)
|
11/12/2023
|
as on 11.12.2023 hot copy not received so, kindly submit the 5 Nos of Proposal hot cop
|
|
6
|
User Agency (mohan.ramalingam@stl.tech)
|
REPLY
|
DFO (Cuddalore)
|
03/07/2024
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Cuddalore)
|
EDS
|
User Agency (mohan.ramalingam@stl.tech)
|
10/07/2024
|
as on 10.07.2024 hot copy not received so, kindly submit the 5 Nos of Proposal hot cop
|
|
8
|
User Agency (mohan.ramalingam@stl.tech)
|
REPLY
|
DFO (Cuddalore)
|
10/07/2024
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Cuddalore)
|
EDS
|
User Agency (mohan.ramalingam@stl.tech)
|
23/07/2024
|
kindly submit the non land availability certificate with collector sign
|
|