  (i). Proposal No. : FP/SK/TRANS/46714/2020              (ii). Name of Project for which Forest Land is required : Diversion of 0.117 Ha of forest land for 66kV SC Singhik to Mangan TL under CSSTDS in North Sikkim by Energy & Power Deptt., Sikkim              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Energy and Power Department Government of Sikkim is constructing 19 No's of Substation and 29 No's of Transmission Line in Sikkim for integrated power development and in the scheme the construction of 66 KV S/C Singhik to ManganTL is one of it.              (iv). File no. : CSSTDS-03/2021/FC              (v). State : Sikkim              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.117
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/SK/TRANS/46714/202001/07/202001/07/2020   04/07/2020   07/07/2020   14/07/2020 North Territorial :14/07/2020Territorial:
  24/12/2020 (North Territorial)

Sikkim:
15/01/2021
Sikkim:
15/02/2021
Kolkata:
17/02/2021
01/03/2021
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : Regional Office .