  (i). Proposal No. : FP/SK/TRANS/34865/2018              (ii). Name of Project for which Forest Land is required : Diversion of 3.654 Ha of Forest land for 66KV Double Circuit Transmission Line from Samardong to Kumrek under Comprehensive Scheme for Strengthening of Transmission and Distribution System in Sikkim by Energy and Power Department Government of Sikkim.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : nergy and Power Department Government of Sikkim is constructing 19 No's of Substation and 29 No's of Transmission Line in Sikkim for integrated power development and in the scheme the construction of 66kV D/C Samardong to Kumrek Transmission Line is one of it.              (iv). File no. : 3-SK B 097/2019-SHI              (v). State : Sikkim              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 3.6538
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/SK/TRANS/34865/201825/08/201828/08/2018   21/09/2018   22/09/2018   22/09/2018

East Territorial :27/09/2018


South Territorial :27/09/2018

Territorial:
  06/03/2019 (East Territorial)

Territorial:
  13/05/2019 (South Territorial)

Sikkim:
13/05/2019
Sikkim:
11/06/2019
Kolkata:
11/06/2019
18/06/2020
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Kolkata) on:16/01/2020  
Replied by State Government(Sikkim) on:13/02/2020  
Query raised by Regional Office (Kolkata) on:04/05/2020  
Replied by State Government(Sikkim) on:17/06/2020  
NOTE:- Stage-I Approval accorded by : Regional Office .