TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/SK/TRANS/33208/2018              (ii). Name of Project for which Forest Land is required : Diversion of 1.422 Ha of Forest land for 66KV Double Circuit Transmission Line from Rorathang to Pakyong under comprehensive scheme for strengthening of transmission and distribution system in sikkim by Energy and Power Department Government of Sikkim.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Energy and Power Department Government of Sikkim is constructing 19 No's of Substation and 29 No's of Transmission Line in Sikkim for integrated power development and in the scheme the construction of 66 KV D/C Rorathang LILO (Pakyong-Rongli) Transmission Line is one of it.              (iv). File no. : 3-SK B 028/2019-SHI              (v). State : Sikkim              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.422
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/SK/TRANS/33208/201822/04/201824/04/2018   20/06/2018   22/06/2018   13/08/2018 East Territorial :13/08/2018Territorial:
  15/11/2018 (East Territorial)

Sikkim:
07/01/2019
Sikkim:
07/01/2019
Kolkata:
10/01/2019
20/05/2019
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Kolkata) on:28/01/2019  
Replied by State Government(Sikkim) on:04/04/2019  
NOTE:- Stage-I Approval accorded by : Regional Office .