TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/SK/TRANS/10009/2015              (ii). Name of Project for which Forest Land is required : Diversion of 40.9299 Ha.of Forest land for Construction of 400kV Transmission Line Teesta III to Kishanganj Loop Out at RANGPO by POWERGRID CORPORATION OF INDIA LIMITED (a Govt. of India Enterprise).              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Power Grid Corporation of India Limited (a Govt. of India Enterprise) is entrusted to construct Two no. of sub-station and Few transmission lines for Transfer of POWER from generation projects in Sikkim to NR/WR (Part-B) in state of Sikkim sanctioned by the government of India out of above one of th              (iv). File no. : 3-SK C 023/2019-SHI              (v). State : Sikkim              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 40.9299
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/SK/TRANS/10009/201510/03/201507/05/2015   11/08/2015   13/08/2015   13/08/2015   South Territorial :24/08/2015Territorial:
  20/11/2018 (South Territorial)

Sikkim:
20/11/2018
Sikkim:
27/11/2018
Kolkata:
19/12/2018
23/01/2019
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (South Territorial) on:25/08/2015  
Replied by UA on :04/11/2017  
Query raised by DFO (South Territorial) on:29/06/2018  
Replied by UA on :03/07/2018  
NOTE:- Stage-I Approval accorded by : Regional Office .