Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Regional Office
|
EDS
|
State secretary
|
29/06/2021
|
1. The soft copy of KML/GPS coordinated of the proposed diversion and CA sites polygon is to be submitted.
2. The proposed diversion area is near to river. Therefore, quantity of Muck to be generated with GPS coordinates of muck disposal area/Muck disposal plan and distance from river area is to be submitted.
3. Forest Right Act, 2006 certificate.
4. The ROW and length of road is to be mentioned clearly.
5. The technically approved CA scheme and duly singed copy is to be submitted.
6. The technically approved and duly signed original copy of avenue plantation scheme for the road side plantation is to be submitted.
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
12/08/2021
|
Please Upload Additional Information.
|
|
3
|
Nodal Officer
|
EDS
|
CF (Territorial)
|
12/08/2021
|
Please upload Additional Information.
|
|
4
|
CF (Territorial)
|
EDS
|
DFO (North Territorial)
|
12/08/2021
|
Please Upload Additional Information.
|
|
5
|
DFO (North Territorial)
|
REPLY
|
CF (Territorial)
|
12/08/2021
|
Additional information has been uploaded.
|
|
6
|
CF (Territorial)
|
REPLY
|
Nodal Officer
|
12/08/2021
|
Additional information has been uploaded.
|
|
7
|
Nodal Officer
|
REPLY
|
State secretary
|
12/08/2021
|
Additional Information has been uploaded
|
|
8
|
State secretary
|
REPLY
|
Regional Office
|
12/08/2021
|
Additional Information has been uploaded.
|
|
9
|
Regional Office
|
EDS
|
State secretary
|
19/08/2021
|
Additional information
|
|
10
|
State secretary
|
REPLY
|
Regional Office
|
08/09/2021
|
EDS reply of vide letter no SK/ROAD-15/2021/FC/172 dated 19.8.21
|
|