TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/SK/ROAD/40504/2019              (ii). Name of Project for which Forest Land is required : Diversion of 0.308 ha of forest land for construction of road from Singleybong to Bageykhola (4km to 5km) via L. Singleybong by R&B Deptt. GoS              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.409 ha of forest land for construction of road from Singleybong to Bageykhola (4km to 5km) via L. Singleybong by R&B Deptt. GoS              (iv). File no. : 1837/FCA/FEWMD              (v). State : Sikkim              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.308
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/SK/ROAD/40504/201903/06/201904/06/2019   22/10/2019   22/10/2019   22/10/2019 East Territorial :25/11/2019Territorial:
  28/11/2019 (East Territorial)

Sikkim:
12/03/2020
Sikkim:
11/05/2020
15/05/2020
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .
Close(X)
Close(X)
Please wait ...