A. General Details
  (i). Proposal No. : FP/SK/ROAD/154584/2022              (ii). Name of Project for which Forest Land is required : Diversion of 116.1 ha forest land for widening/upgradation of existing road (NH 310A) to NHDL specification with paved shoulder from Yumthang of Design km 52+808 to Yume Samdang Border (Zero point) of design 84.160 kmby BRO in Sikkim              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Falls under financial PKG-VI which starts from Yumthang of 52.808 km and ends on Yume Sangdang of 84.160 km. It is widening of existing road with improved vehicle design speed and importantly it is for movement of Defense Vehicle for the national security of India since the area is near to the Inter              (iv). State : Sikkim              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 116.1
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/SK/ROAD/154584/202218/04/202204/08/2022  21/06/2022  12/05/2022  12/05/2022  28/04/2022   30/08/2022  28/07/2022  12/05/2022  12/05/2022  28/04/2022   23/05/2022   08/06/2022 North Territorial :02/09/2022Territorial:
  16/02/2023 (North Territorial)

  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Territorial) on:16/02/2023  
Replied by DFO (North Territorial) on:27/07/2023  
Query raised by Circle (Territorial) on:04/12/2023  
Replied by DFO (North Territorial) on:04/12/2023  
Query raised by DFO (North Territorial) on:12/10/2022  
Replied by UA on :04/11/2022  
NOTE:- Proposal is pending at CF .