TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/SK/ROAD/122332/2021              (ii). Name of Project for which Forest Land is required : Diversion of 1.0428 ha of forest land for construction of RCR from Narkhola to Upper Narkhola & Lower Narkhola in West Sikkim              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The new road connectivity “Narkhola to Upper Narkhola & Lower Narkhola” under West Sikkim has been sanctioned under the PMGSY scheme during the year 2016-17 under Rural Development Department with amounting to Rs. 856.89 Lakh. It is a genuine need to overcome the poverty and increase the socio-econo              (iv). File no. : SK/ROAD-72/2021/FC              (v). State : Sikkim              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.0428
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/SK/ROAD/122332/202123/02/202105/03/2021   01/04/2021   01/04/2021   01/04/2021 West Territorial :01/04/2021Territorial:
  27/08/2021 (West Territorial)

Sikkim:
27/08/2021
Sikkim:
27/08/2021
Kolkata:
14/09/2021
31/03/2022
By :Regional Office
Sikkim
23/01/2025
29/01/2025
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Kolkata) on:15/12/2021  
Replied by State Government(Sikkim) on:02/03/2022  
Query raised by State Government (Sikkim) on:01/03/2022  
Replied by Nodal Officer (Sikkim) on:02/03/2022  
Query raised by Nodal Officer (Sikkim) on:01/03/2022  
Replied by Circle(Territorial) on:02/03/2022  
Query raised by Circle (Territorial) on:01/03/2022  
Replied by DFO (West Territorial) on:02/03/2022  
Query raised by DFO (West Territorial) on:01/03/2022  
Replied by UA on :02/03/2022  
NOTE:- Stage-II Approval accorded by : Regional Office .