Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/SK/ROAD/121301/2021              (ii). Name of Project for which Forest Land is required : Diversion of 0.10033 ha of forest land for the construction of PMGSY road from SPWD Road to Dipawalitar Upper Tumin Via Ramakrishna Mandir in East Sikkim by RDD, GoS              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : PMGSY Road Which connects the pwd road due to which the people of this area can go to the cities and also it will help them for the daily basic needs for going schools,Hospitals etc              (iv). File no. : SK/ROAD-48/2021/FC              (v). State : Sikkim              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.10033
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/SK/ROAD/121301/202101/02/202103/02/2021   25/02/2021   25/02/2021   25/02/2021 East Territorial :25/02/2021Territorial:
  12/04/2021 (East Territorial)

Sikkim:
09/07/2021
Sikkim:
09/07/2021
Kolkata:
09/07/2021
31/03/2022
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Kolkata) on:30/07/2021  
Replied by State Government(Sikkim) on:19/11/2021  
Query raised by Regional Office (Kolkata) on:29/12/2021  
Replied by State Government(Sikkim) on:02/03/2022  
Query raised by State Government (Sikkim) on:30/09/2021  
Replied by Nodal Officer (Sikkim) on:19/11/2021  
Query raised by State Government (Sikkim) on:01/03/2022  
Replied by Nodal Officer (Sikkim) on:02/03/2022  
Query raised by Nodal Officer (Sikkim) on:09/07/2021  
Replied by Circle(Territorial) on:09/07/2021  
Query raised by Nodal Officer (Sikkim) on:30/09/2021  
Replied by Circle(Territorial) on:30/09/2021  
Query raised by Nodal Officer (Sikkim) on:30/09/2021  
Replied by Circle(Territorial) on:19/11/2021  
Query raised by Nodal Officer (Sikkim) on:01/03/2022  
Replied by Circle(Territorial) on:02/03/2022  
Query raised by Circle (Territorial) on:11/11/2021  
Replied by DFO (East Territorial) on:19/11/2021  
Query raised by Circle (Territorial) on:01/03/2022  
Replied by DFO (East Territorial) on:02/03/2022  
Query raised by DFO (East Territorial) on:01/03/2022  
Replied by UA on :02/03/2022  
NOTE:- Stage-I Approval accorded by : Regional Office .