  (i). Proposal No. : FP/SK/Others/7800/2014              (ii). Name of Project for which Forest Land is required : Landfill site for Solid Waste              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The present dumping site at Martam is over flowing due to huge accomodation of solid waste generated from urban areas in an around Gangtok. The alternative land fill site is thus required and is identified at Bhasmay RF 6 km away from Rangpo, East Sikkim              (iv). State : Sikkim              (v). Category of the Project : Others              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 1.39
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/SK/Others/7800/201406/11/2014aa27/11/2014   19/07/2016 East Territorial :28/07/2016Territorial:
  04/11/2016 (East Territorial)

  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Territorial) on:02/05/2022  
NOTE:- Proposal is pending at DFO due to EDS raised by CF .