Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Jaipur (South) Territorial)
|
EDS
|
User Agency (eepdiin@gmail.com)
|
18/12/2020
|
no marking on the site
|
|
2
|
User Agency (eepdiin@gmail.com)
|
REPLY
|
DFO (Jaipur (South) Territorial)
|
08/01/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Jaipur (South) Territorial)
|
EDS
|
User Agency (eepdiin@gmail.com)
|
01/02/2021
|
revenue details not completed.
|
|
4
|
User Agency (eepdiin@gmail.com)
|
REPLY
|
DFO (Jaipur (South) Territorial)
|
03/02/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Jaipur (South) Territorial)
|
EDS
|
User Agency (eepdiin@gmail.com)
|
12/02/2021
|
office letter no 1115 dated 12.02.2021
|
|
6
|
User Agency (eepdiin@gmail.com)
|
REPLY
|
DFO (Jaipur (South) Territorial)
|
15/02/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Jaipur (South) Territorial)
|
EDS
|
User Agency (eepdiin@gmail.com)
|
05/03/2021
|
The correction have been made as per the instruction received
|
|
8
|
User Agency (eepdiin@gmail.com)
|
REPLY
|
DFO (Jaipur (South) Territorial)
|
09/03/2021
|
The correction have been made as per the instruction received
|
|
9
|
CF (Jaipur)
|
EDS
|
DFO (Jaipur (South) Territorial)
|
22/03/2021
|
pls furnish the info.
|
|
10
|
DFO (Jaipur (South) Territorial)
|
REPLY
|
CF (Jaipur)
|
24/03/2021
|
all documents are completed
|
|
11
|
State secretary
|
EDS
|
Nodal Officer
|
29/04/2021
|
please eds reply
|
|
12
|
Nodal Officer
|
EDS
|
CF (Jaipur)
|
05/05/2021
|
Please find attached EDS for compliance.
|
|
13
|
CF (Jaipur)
|
EDS
|
DFO (Jaipur (South) Territorial)
|
17/05/2021
|
Pls, furnish the EDS.
|
|
14
|
DFO (Jaipur (South) Territorial)
|
EDS
|
User Agency (eepdiin@gmail.com)
|
19/05/2021
|
Please clarify regarding proposal. The point is mentioned attached letter.
|
|
15
|
User Agency (eepdiin@gmail.com)
|
REPLY
|
DFO (Jaipur (South) Territorial)
|
27/05/2021
|
The correction have been made as per the instruction received
|
|
16
|
DFO (Jaipur (South) Territorial)
|
REPLY
|
CF (Jaipur)
|
27/05/2021
|
Regarding proposal no. 42602 reply received by user agency is attached for necessary action
|
|
17
|
CF (Jaipur)
|
REPLY
|
Nodal Officer
|
31/05/2021
|
dcf has been submitted eds via his letter no. 4720 dated 27.5.2021.
|
|
18
|
Nodal Officer
|
EDS
|
CF (Jaipur)
|
24/06/2021
|
DCF has to submit detailed report of the construction of pump house and he has to verify that no violation of FCA ACT 1980 in construction of it.
|
|
19
|
CF (Jaipur)
|
EDS
|
DFO (Jaipur (South) Territorial)
|
08/07/2021
|
DCF has to submit detailed report of the construction of pump house and he has to verify that no violation of FCA ACT 1980 in construction of it.
|
|
20
|
DFO (Jaipur (South) Territorial)
|
EDS
|
User Agency (eepdiin@gmail.com)
|
15/07/2021
|
Provide documents regarding pump house construction
|
|
21
|
User Agency (eepdiin@gmail.com)
|
REPLY
|
DFO (Jaipur (South) Territorial)
|
23/07/2021
|
The correction have been made as per the instruction received
|
|
22
|
DFO (Jaipur (South) Territorial)
|
REPLY
|
CF (Jaipur)
|
27/07/2021
|
Reply received by user agency is attached for necessary action
|
|
23
|
CF (Jaipur)
|
REPLY
|
Nodal Officer
|
18/08/2021
|
Sir, DCF has submitted detailed report of the construction of pump house.
|
|
24
|
Nodal Officer
|
REPLY
|
State secretary
|
31/08/2021
|
The EDS compliance report is attached.
|
|