Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bundi Territorial)
|
EDS
|
User Agency (rrdoie123@gmail.com)
|
06/02/2023
|
Kindly provide NFL land and related document
|
|
2
|
DFO (Bhilwara Territorial)
|
EDS
|
User Agency (rrdoie123@gmail.com)
|
07/02/2023
|
Please enclosed
|
|
3
|
User Agency (rrdoie123@gmail.com)
|
REPLY
|
DFO (Bundi Territorial)
|
14/02/2023
|
The correction have been made as per the instruction received
|
|
4
|
User Agency (rrdoie123@gmail.com)
|
REPLY
|
DFO (Bhilwara Territorial)
|
14/02/2023
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Bhilwara Territorial)
|
EDS
|
User Agency (rrdoie123@gmail.com)
|
15/02/2023
|
Please find enclosed
|
|
6
|
User Agency (rrdoie123@gmail.com)
|
REPLY
|
DFO (Bhilwara Territorial)
|
16/02/2023
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Bundi Territorial)
|
EDS
|
User Agency (rrdoie123@gmail.com)
|
20/02/2023
|
Kindly provide NFL land and related document
|
|
8
|
User Agency (rrdoie123@gmail.com)
|
REPLY
|
DFO (Bundi Territorial)
|
29/03/2023
|
The correction have been made as per the instruction received
|
|
9
|
CF (Ajmer)
|
EDS
|
DFO (Bhilwara Territorial)
|
18/04/2023
|
Plz reply the following shortcomings noticed
1.In this proposal, the estimate for plantation on NFL for total proposed CA is already given by DCF, Ramgarh Vishdhari Tiger Reserve, Bundi. DCF, Bhilwara also attached estimate for 0.8676 ha. So, Clarify this.
2. The certificate needed by Principal Chief Conservator of Forests, Rajasthan, Jaipur, wide letter no. 1899-2025 dated 26.07.2021 has not been attached by DCF, Bhilwa
|
|
10
|
DFO (Bhilwara Territorial)
|
REPLY
|
CF (Ajmer)
|
01/05/2023
|
letter dated 01-05-23 attached and certificate attached
|
|
11
|
Nodal Officer
|
EDS
|
CF (Ajmer)
|
11/05/2023
|
Kindly provide information as per attached document.
|
|
12
|
Nodal Officer
|
EDS
|
CF (Kota)
|
11/05/2023
|
Kindly provide information as per attached document.
|
|
13
|
Nodal Officer
|
EDS
|
CF (Kota Wildlife)
|
11/05/2023
|
Kindly provide information as per attached document.
|
|
14
|
CF (Kota)
|
EDS
|
DFO (Bundi Territorial)
|
12/05/2023
|
Kindly provide information as per attached document.
|
|
15
|
CF (Ajmer)
|
EDS
|
DFO (Bhilwara Territorial)
|
12/05/2023
|
Kindly provide information as per attached document.
|
|
16
|
DFO (Bundi Territorial)
|
EDS
|
User Agency (rrdoie123@gmail.com)
|
12/05/2023
|
Kindly provide information as per attached document.
|
|
17
|
User Agency (rrdoie123@gmail.com)
|
REPLY
|
DFO (Bundi Territorial)
|
15/05/2023
|
The correction have been made as per the instruction received
|
|
18
|
DFO (Bundi Territorial)
|
EDS
|
User Agency (rrdoie123@gmail.com)
|
17/05/2023
|
Kindly provide information as per attached document.
|
|
19
|
User Agency (rrdoie123@gmail.com)
|
REPLY
|
DFO (Bundi Territorial)
|
29/05/2023
|
The correction have been made as per the instruction received
|
|
20
|
DFO (Bundi Territorial)
|
REPLY
|
CF (Kota)
|
01/06/2023
|
The correction have been made as per the instruction received
|
|
21
|
CF (Kota Wildlife)
|
EDS
|
DFO (Ramgarh Vishdhari Tiger Reserve (Core), Bundi)
|
06/06/2023
|
Comply with the eds raised by Nodel Officer.
|
|
22
|
DFO (Bhilwara Territorial)
|
REPLY
|
CF (Ajmer)
|
06/06/2023
|
please find Attech
|
|
23
|
DFO (Ramgarh Vishdhari Tiger Reserve (Core), Bundi)
|
REPLY
|
CF (Kota Wildlife)
|
07/06/2023
|
correction has been made as instruction received.
|
|
24
|
CF (Kota Wildlife)
|
REPLY
|
Nodal Officer
|
08/06/2023
|
The reply of EDS has been submitted by User Agency and DCF, RVTR, Bundi. It is being forwarded with the consent of this office,
|
|
25
|
CF (Ajmer)
|
REPLY
|
Nodal Officer
|
13/06/2023
|
Kindly find attached the reply of EDS for further necessary action
|
|
26
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
13/06/2023
|
The correction have been made as per the instruction received.
|
|
27
|
Nodal Officer
|
EDS
|
CF (Kota)
|
21/06/2023
|
Kindly provide information as per attached document.
|
|
28
|
Nodal Officer
|
EDS
|
CF (Kota Wildlife)
|
21/06/2023
|
Kindly provide information as per attached document.
|
|
29
|
CF (Kota)
|
EDS
|
DFO (Bundi Territorial)
|
23/06/2023
|
Kindly provide information as per attached document.
|
|
30
|
CF (Kota Wildlife)
|
EDS
|
DFO (Ramgarh Vishdhari Tiger Reserve (Core), Bundi)
|
26/06/2023
|
Kindly provide information as per attached document.
|
|
31
|
DFO (Ramgarh Vishdhari Tiger Reserve (Core), Bundi)
|
REPLY
|
CF (Kota Wildlife)
|
26/06/2023
|
Sir complete compliance as your order
|
|
32
|
DFO (Bundi Territorial)
|
REPLY
|
CF (Kota)
|
26/06/2023
|
The correction have been made as per the instruction received
|
|
33
|
CF (Kota)
|
EDS
|
DFO (Bundi Territorial)
|
26/06/2023
|
Kindly provide information as per attached document.
|
|
34
|
DFO (Bundi Territorial)
|
REPLY
|
CF (Kota)
|
26/06/2023
|
The correction have been made as per the instruction received
|
|
35
|
CF (Kota Wildlife)
|
REPLY
|
Nodal Officer
|
28/06/2023
|
correction have been made as instruction received on dated 21.06.2023
|
|
36
|
CF (Kota)
|
EDS
|
DFO (Bundi Territorial)
|
28/06/2023
|
Point no 8 iv revision of part-2 is expected.
|
|
37
|
DFO (Bundi Territorial)
|
REPLY
|
CF (Kota)
|
28/06/2023
|
The correction have been made as per the instruction received
|
|
38
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
28/06/2023
|
The correction have been made as per the instruction received date 21.06.2023
|
|
39
|
Nodal Officer
|
EDS
|
CF (Kota Wildlife)
|
04/07/2023
|
1. NPV certificate is wrong
2. Working plan prescription not attached.
|
|
40
|
CF (Kota Wildlife)
|
EDS
|
DFO (Ramgarh Vishdhari Tiger Reserve (Core), Bundi)
|
04/07/2023
|
NPV certificate is wrong 2. Working plan prescription not attached
|
|
41
|
DFO (Ramgarh Vishdhari Tiger Reserve (Core), Bundi)
|
REPLY
|
CF (Kota Wildlife)
|
05/07/2023
|
sir complete compliance.
|
|
42
|
CF (Kota Wildlife)
|
EDS
|
DFO (Ramgarh Vishdhari Tiger Reserve (Core), Bundi)
|
05/07/2023
|
EDS letter is not submitted. Kindly submit
|
|
43
|
DFO (Ramgarh Vishdhari Tiger Reserve (Core), Bundi)
|
REPLY
|
CF (Kota Wildlife)
|
05/07/2023
|
complete compliance .
|
|
44
|
CF (Kota Wildlife)
|
REPLY
|
Nodal Officer
|
06/07/2023
|
EDS compliance completed as per your order
|
|