TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/RJ/TRANS/40706/2019              (ii). Name of Project for which Forest Land is required : 33 KV lotiyana line for 33/11 kv gss lotiyana from 132/33 kv gss badoliya to lotiyana              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : 33 KV Lotiyana line for 33/11 kv GSS lotiyana from 132/33 kv gss badoliya to lotiyana for providning rural agriculture connection to the villagers and house hold electrification in bhainsroadgarh block of chittorgarh distt. under DDUGJY project              (iv). State : Rajasthan              (v). Category of the Project : Transmission Line              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 6.72
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/RJ/TRANS/40706/201912/07/201923/10/2019  20/08/2019   26/11/2019  06/09/2019   13/12/2019   05/01/2020 Chittorgarh Territorial :06/01/2020
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Chittorgarh Territorial) on:24/02/2020  
NOTE:- Proposal is pending at DELISTED (due to non-reply of EDS by UA within 90 days) due to EDS raised by DELISTED .