Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Dungarpur)
|
EDS
|
User Agency (xenpwddpr@yahoo.in)
|
10/11/2015
|
The Proposal examined in the presence of ACF, AEn PWD and Patwari. The following errors were found -1. Road marking in forest area not enclosed. Only the road passing through revenue areas is marked and enclosed. 2. Khasra Jamabandi enclosed and shown as forest khasras is erroneous.Chainages marked on Revenue maps are not correct. Details are being sent to you by hard copy.kindly review the proposal and rectify.
|
|
2
|
User Agency (xenpwddpr@yahoo.in)
|
REPLY
|
DFO (Dungarpur)
|
12/07/2016
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Dungarpur)
|
EDS
|
User Agency (xenpwddpr@yahoo.in)
|
19/07/2016
|
1.Submit point wise reply in response to letter No.8670 dated 10.11.2015 by online as well as hard copy
2.Reason for increasing area of forest land from 8.32 ha. to 12.528 ha.
3.Enclose the certificate requiring forest land area of 12.528 ha.
4.Enclose the FRA certificate for required forest land area of 12.528 ha.
kindly submit the hard copies
|
|
4
|
User Agency (xenpwddpr@yahoo.in)
|
REPLY
|
DFO (Dungarpur)
|
22/07/2016
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Dungarpur)
|
EDS
|
User Agency (xenpwddpr@yahoo.in)
|
25/07/2016
|
1.Enclose the certificate requiring forest land area of 12.528 ha.
2.Enclose the FRA certificate for required forest land area of 12.528 ha.
|
|
6
|
User Agency (xenpwddpr@yahoo.in)
|
REPLY
|
DFO (Dungarpur)
|
02/08/2016
|
The correction have been made as per the instruction received
|
|
7
|
Nodal Officer
|
EDS
|
CF (Udaipur)
|
08/08/2016
|
Some additional information are required. Kindly provide information as per attached document.
|
|
8
|
CF (Udaipur)
|
EDS
|
DFO (Dungarpur)
|
09/08/2016
|
please provide information sought by nodal officer
|
|
9
|
DFO (Dungarpur)
|
EDS
|
User Agency (xenpwddpr@yahoo.in)
|
11/08/2016
|
Please correct the document as sought by nodal officer
|
|
10
|
User Agency (xenpwddpr@yahoo.in)
|
REPLY
|
DFO (Dungarpur)
|
19/08/2016
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Dungarpur)
|
EDS
|
User Agency (xenpwddpr@yahoo.in)
|
20/08/2016
|
upload the revised order of allotment of CA land in lie of forest land diverted for this proposed project
|
|
12
|
User Agency (xenpwddpr@yahoo.in)
|
REPLY
|
DFO (Dungarpur)
|
20/08/2016
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Dungarpur)
|
EDS
|
User Agency (xenpwddpr@yahoo.in)
|
20/08/2016
|
Please upload the revised order of allotment of CA land in lie of forest land diverted for this proposed project
|
|
14
|
User Agency (xenpwddpr@yahoo.in)
|
REPLY
|
DFO (Dungarpur)
|
20/08/2016
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Dungarpur)
|
REPLY
|
CF (Udaipur)
|
20/08/2016
|
The correction have been made by user agency as sought by nodal officer
|
|
16
|
CF (Udaipur)
|
REPLY
|
Nodal Officer
|
22/08/2016
|
The proposal is again being forwarded
|
|
17
|
Nodal Officer
|
EDS
|
CF (Udaipur)
|
19/09/2016
|
Some additional information are required. Kindly provide.
|
|
18
|
CF (Udaipur)
|
EDS
|
DFO (Dungarpur)
|
20/09/2016
|
kindly examine and reply
|
|
19
|
DFO (Dungarpur)
|
EDS
|
User Agency (xenpwddpr@yahoo.in)
|
20/09/2016
|
Please correct the document as sought by nodal officer
|
|
20
|
User Agency (xenpwddpr@yahoo.in)
|
REPLY
|
DFO (Dungarpur)
|
20/10/2016
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Dungarpur)
|
EDS
|
User Agency (xenpwddpr@yahoo.in)
|
20/10/2016
|
kindly upload the documents for point no.3 and point no.5 as sought by nodal officer
|
|
22
|
User Agency (xenpwddpr@yahoo.in)
|
REPLY
|
DFO (Dungarpur)
|
20/10/2016
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Dungarpur)
|
EDS
|
User Agency (xenpwddpr@yahoo.in)
|
20/10/2016
|
kindly upload the documents for point no.3 at point no k-i of the proposal in part I
|
|
24
|
User Agency (xenpwddpr@yahoo.in)
|
REPLY
|
DFO (Dungarpur)
|
20/10/2016
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Dungarpur)
|
EDS
|
User Agency (xenpwddpr@yahoo.in)
|
20/10/2016
|
kindly upload the the geo referenced map with the signatures
|
|
26
|
User Agency (xenpwddpr@yahoo.in)
|
REPLY
|
DFO (Dungarpur)
|
21/10/2016
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Dungarpur)
|
REPLY
|
CF (Udaipur)
|
27/10/2016
|
submission of EDs by the user agency as soughted by the nodal officer
|
|
28
|
CF (Udaipur)
|
REPLY
|
Nodal Officer
|
02/11/2016
|
The case is being submitted as forwarded by dfo
|
|
29
|
Nodal Officer
|
EDS
|
CF (Udaipur)
|
18/11/2016
|
Kindly provide additional information as per attached document.
|
|
30
|
CF (Udaipur)
|
EDS
|
DFO (Dungarpur)
|
22/11/2016
|
Forwarded to ensure the compliance and submit at earliest.
|
|
31
|
DFO (Dungarpur)
|
EDS
|
User Agency (xenpwddpr@yahoo.in)
|
22/11/2016
|
Kindly fulfill the quaires raised by nodal officer
|
|
32
|
User Agency (xenpwddpr@yahoo.in)
|
REPLY
|
DFO (Dungarpur)
|
04/12/2016
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Dungarpur)
|
REPLY
|
CF (Udaipur)
|
06/12/2016
|
Submission of EDs as soughted by the nodal officer
|
|
34
|
CF (Udaipur)
|
REPLY
|
Nodal Officer
|
10/12/2016
|
Reply to EDS as send by DCf Dungarpur letter dated6.12.16 is being forwarded with consent of this office
|
|