TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/RJ/ROAD/42427/2019              (ii). Name of Project for which Forest Land is required : Construction of A/R Patri to Bhatgoun road under PMGSY Scheme              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of A/R Patri to Bhatgoun road under PMGSY Scheme              (iv). State : Rajasthan              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 1.5
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/RJ/ROAD/42427/201914/10/201921/11/2019   05/01/2020   16/01/2020   18/08/2020 Baran Territorial :19/08/2020Kota:
  10/09/2023 (Baran Territorial)

  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Kota) on:14/09/2023  
Replied by DFO (Baran Territorial) on:21/09/2023  
Query raised by Circle (Kota) on:27/09/2023  
Replied by DFO (Baran Territorial) on:21/02/2024  
Query raised by Circle (Kota) on:04/03/2024  
Replied by DFO (Baran Territorial) on:01/04/2024  
Query raised by Circle (Kota) on:23/04/2024  
Replied by DFO (Baran Territorial) on:26/09/2024  
Query raised by Circle (Kota) on:26/09/2024  
Replied by DFO (Baran Territorial) on:10/10/2024  
Query raised by Circle (Kota) on:14/10/2024  
Replied by DFO (Baran Territorial) on:25/10/2024  
Query raised by Circle (Kota) on:25/10/2024  
Replied by DFO (Baran Territorial) on:04/11/2024  
Query raised by Circle (Kota) on:05/11/2024  
Replied by DFO (Baran Territorial) on:08/11/2024  
Query raised by Circle (Kota) on:08/11/2024  
Replied by DFO (Baran Territorial) on:13/11/2024  
Query raised by Circle (Kota) on:13/11/2024  
Replied by DFO () on:  
Query raised by DFO (Baran Territorial) on:04/11/2020  
Replied by UA on :26/12/2022  
Query raised by DFO (Baran Territorial) on:29/05/2023  
Replied by UA on :27/07/2023  
Query raised by DFO (Baran Territorial) on:30/10/2023  
Replied by UA on :23/01/2024  
Query raised by DFO (Baran Territorial) on:03/05/2024  
Replied by UA on :17/09/2024  
Query raised by DFO (Baran Territorial) on:14/11/2024  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by CF .
Close(X)
Close(X)
Please wait ...