Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Ajmer)
|
16/03/2021
|
1. CCF has to upload and attach site inspection report.
2. Approved lay out plan by MoRTH should be attached in hard copy in Part I of the proposal.
|
|
2
|
CF (Ajmer)
|
EDS
|
DFO (Nagaur Territorial)
|
22/03/2021
|
Plz send the reply for the following EDS received from nodal office.
1. Approved lay out plan by MoRTH should be attached in hard copy in Part I of the proposal.
|
|
3
|
DFO (Nagaur Territorial)
|
EDS
|
User Agency (petrolpumpproposalsfcaiocl@yahoo.co.in)
|
26/03/2021
|
Plz send the reply for the following EDS received from nodal office. 1. Approved lay out plan by MoRTH should be attached in hard copy in Part I of the proposal.
|
|
4
|
User Agency (petrolpumpproposalsfcaiocl@yahoo.co.in)
|
REPLY
|
DFO (Nagaur Territorial)
|
15/04/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Nagaur Territorial)
|
REPLY
|
CF (Ajmer)
|
23/04/2021
|
Complete EDS
|
|
6
|
CF (Ajmer)
|
EDS
|
DFO (Nagaur Territorial)
|
26/04/2021
|
Please brief
|
|
7
|
DFO (Nagaur Territorial)
|
REPLY
|
CF (Ajmer)
|
27/04/2021
|
The correction have been made as per the instruction received
|
|
8
|
CF (Ajmer)
|
EDS
|
DFO (Nagaur Territorial)
|
25/05/2021
|
The CA scheme for 0.5 ha. forest land is seems to be proposed in proportionate of model of CA for 50 ha. which does not fit for small area. It should be as per he area and requirement of the site. Amended CA scheme should be proposed.
|
|
9
|
DFO (Nagaur Territorial)
|
REPLY
|
CF (Ajmer)
|
21/06/2021
|
Revise Ca scheme
|
|
10
|
CF (Ajmer)
|
REPLY
|
Nodal Officer
|
22/06/2021
|
Copy of site visit by CCF, Ajmer
|
|
11
|
Nodal Officer
|
EDS
|
CF (Ajmer)
|
23/06/2021
|
CCF has not uploaded his site inspectionc report.
|
|
12
|
CF (Ajmer)
|
REPLY
|
Nodal Officer
|
23/06/2021
|
Site inspection report uploaded
|
|
13
|
Nodal Officer
|
EDS
|
CF (Ajmer)
|
09/07/2021
|
CA scheme is not justified. For planting of 100 plants , scheme of Rs. 90000 is being taken. More than 4 times scheme is not justified. Please get it done rational.
|
|
14
|
CF (Ajmer)
|
EDS
|
DFO (Nagaur Territorial)
|
23/07/2021
|
Plz revise CA scheme
|
|
15
|
DFO (Nagaur Territorial)
|
REPLY
|
CF (Ajmer)
|
12/08/2021
|
Revise CA scheme
|
|
16
|
CF (Ajmer)
|
REPLY
|
Nodal Officer
|
18/08/2021
|
Revise CA scheme
|
|
17
|
State secretary
|
EDS
|
Nodal Officer
|
23/09/2021
|
please eds reply
|
|
18
|
Nodal Officer
|
EDS
|
CF (Ajmer)
|
23/09/2021
|
Please find attached EDS for compliance.
|
|
19
|
CF (Ajmer)
|
EDS
|
DFO (Nagaur Territorial)
|
23/09/2021
|
Please find attached EDS for compliance.
|
|
20
|
DFO (Nagaur Territorial)
|
EDS
|
User Agency (petrolpumpproposalsfcaiocl@yahoo.co.in)
|
28/09/2021
|
Please find attached EDS for compliance.
|
|
21
|
User Agency (petrolpumpproposalsfcaiocl@yahoo.co.in)
|
REPLY
|
DFO (Nagaur Territorial)
|
06/10/2021
|
The correction have been made as per the instruction received
|
|
22
|
DFO (Nagaur Territorial)
|
REPLY
|
CF (Ajmer)
|
14/10/2021
|
EDS Reply
|
|
23
|
CF (Ajmer)
|
REPLY
|
Nodal Officer
|
25/10/2021
|
Plz find attached the reply of EDS.
|
|
24
|
Nodal Officer
|
REPLY
|
State secretary
|
28/10/2021
|
Please find attached EDS compliance report.
|
|