Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Kota)
|
EDS
|
DFO (Jhalawar Territorial)
|
09/02/2018
|
Correct site inspection report is requirement
|
|
2
|
DFO (Jhalawar Territorial)
|
REPLY
|
CF (Kota)
|
10/02/2018
|
correction have been made .
|
|
3
|
Nodal Officer
|
EDS
|
CF (Kota)
|
23/02/2018
|
Kindly provide hard copy of the proposal
|
|
4
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
26/02/2018
|
hard copy forwarded for this office wide letter 1539 dt. 15.02.2018
|
|
5
|
Nodal Officer
|
EDS
|
CF (Kota)
|
06/03/2018
|
Kindly provide information as per attached document.
|
|
6
|
CF (Kota)
|
EDS
|
DFO (Jhalawar Territorial)
|
08/03/2018
|
Kindly provide information as per attached document.
|
|
7
|
DFO (Jhalawar Territorial)
|
EDS
|
User Agency (pwdkhanpur@gmail.com)
|
12/03/2018
|
Kindly provide information as per attached document.
|
|
8
|
User Agency (pwdkhanpur@gmail.com)
|
REPLY
|
DFO (Jhalawar Territorial)
|
24/03/2018
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Jhalawar Territorial)
|
REPLY
|
CF (Kota)
|
03/04/2018
|
The correction have been made as per the instruction received
|
|
10
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
06/04/2018
|
The correction have been made as per the instruction received by user agency and dcf jhalawar.
|
|
11
|
Nodal Officer
|
EDS
|
CF (Kota)
|
11/04/2018
|
Kindly provide information as per attached document.
|
|
12
|
CF (Kota)
|
EDS
|
DFO (Jhalawar Territorial)
|
12/04/2018
|
Kindly provide information as per attached document.
|
|
13
|
DFO (Jhalawar Territorial)
|
EDS
|
User Agency (pwdkhanpur@gmail.com)
|
13/04/2018
|
Kindly provide information as per attached document.
|
|
14
|
User Agency (pwdkhanpur@gmail.com)
|
REPLY
|
DFO (Jhalawar Territorial)
|
20/04/2018
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Jhalawar Territorial)
|
REPLY
|
CF (Kota)
|
23/04/2018
|
The correction have been made as per the instruction received
|
|
16
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
27/04/2018
|
Correction have been made by user agency and Dcf Jhalawar as per the received instruction.
|
|
17
|
Nodal Officer
|
EDS
|
CF (Kota)
|
11/05/2018
|
Kindly provide corrected CA scheme, Sutaibility Certificate KML file DGPS map of CA
|
|
18
|
CF (Kota)
|
EDS
|
DFO (Jhalawar Territorial)
|
11/05/2018
|
Kindly provide corrected CA scheme, Sutaibility Certificate KML file DGPS map of CA
|
|
19
|
DFO (Jhalawar Territorial)
|
REPLY
|
CF (Kota)
|
11/05/2018
|
Correction has been done as per instruction.
|
|
20
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
11/05/2018
|
Correction has been done by DCF Jhalawar.
|
|