Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Udaipur)
|
19/02/2021
|
1. There is violation in the proposal. A comprehensive report is expected from DCF and CCF has to take note of it in his report.
2. Penal NPV calculation is not given.
3.CCF has to upload his site inspection report.
|
|
2
|
CF (Udaipur)
|
EDS
|
DFO (Banswara Territorial)
|
09/03/2021
|
1. There is violation in the proposal. A comprehensive report is expected from DCF and CCF has to take note of it in his report. 2. Penal NPV calculation is not given. 3.CCF has to upload his site inspection report.
|
|
3
|
DFO (Banswara Territorial)
|
REPLY
|
CF (Udaipur)
|
15/07/2021
|
Please find this office letter no. 6124 dt.15-07-2021 regarding Reply of your EDS dated 9-03-2021
|
|
4
|
CF (Udaipur)
|
REPLY
|
Nodal Officer
|
26/07/2021
|
inspection was done on 08-06-2021. the proposed site is near MP State boundary. User agency has violated the rules and tried to laid sown the cable but the same day forest staff toke action. stopped work, issued FIR and levied penalty which was deposited in Govt. account. but since the user agency has violated the rules penal NPV also need to be taken from them.
|
|
5
|
Nodal Officer
|
EDS
|
CF (Udaipur)
|
13/08/2021
|
The following shortcomings are found in the proposal-
1. What actions are taken against the accused in the matter. Please provide the details. Action taken against accused officers and others should be given.
2. CCF has to upload his site inspection report.
3. Detailed report of violation needs to be provided.
|
|
6
|
CF (Udaipur)
|
EDS
|
DFO (Banswara Territorial)
|
25/08/2021
|
The following shortcomings are found in the proposal- 1. What actions are taken against the accused in the matter. Please provide the details. Action taken against accused officers and others should be given. 2. CCF has to upload his site inspection report. 3. Detailed report of violation needs to be provided.
|
|
7
|
DFO (Banswara Territorial)
|
REPLY
|
CF (Udaipur)
|
07/09/2021
|
Please find this office letter no 9517-20 dated 06-09-2021 regarding reply of EDS dated 25-08-2021 raised by RCCF Udaipur
|
|
8
|
CF (Udaipur)
|
REPLY
|
Nodal Officer
|
15/09/2021
|
eds replied
|
|
9
|
Regional Office
|
EDS
|
State secretary
|
18/01/2022
|
EDS letter dated 18.01.2022
|
|
10
|
State secretary
|
EDS
|
Nodal Officer
|
24/03/2022
|
please eds reply
|
|
11
|
Nodal Officer
|
EDS
|
CF (Udaipur)
|
28/03/2022
|
Please find attached EDS for compliance.
|
|
12
|
CF (Udaipur)
|
EDS
|
DFO (Banswara Territorial)
|
31/03/2022
|
Please find attached EDS for compliance.
|
|
13
|
DFO (Banswara Territorial)
|
REPLY
|
CF (Udaipur)
|
02/05/2022
|
complience report of eds dated 18.01.2022 and our letter 21120 dated 31.03.2022
|
|
14
|
CF (Udaipur)
|
EDS
|
DFO (Banswara Territorial)
|
06/05/2022
|
Please find attached EDS for compliance.
|
|
15
|
DFO (Banswara Territorial)
|
REPLY
|
CF (Udaipur)
|
20/05/2022
|
Please find this office letter no.2968 dated19.05.2022 regarding pointwise reply of MOEF letter dated 18 January 2022
|
|
16
|
CF (Udaipur)
|
EDS
|
DFO (Banswara Territorial)
|
25/05/2022
|
please remove additional kml file in part II point 13
|
|
17
|
DFO (Banswara Territorial)
|
REPLY
|
CF (Udaipur)
|
27/05/2022
|
Additional kml file has been removed in part II as per instructions received from your office.
|
|
18
|
CF (Udaipur)
|
EDS
|
DFO (Banswara Territorial)
|
30/05/2022
|
CA scheme has not uploded completely. Upload the required document from 13-3 to 13-5
|
|
19
|
DFO (Banswara Territorial)
|
REPLY
|
CF (Udaipur)
|
31/05/2022
|
All documents related to CA scheme has been uploded from point no. 13.3 to 13.5
|
|
20
|
CF (Udaipur)
|
REPLY
|
Nodal Officer
|
06/06/2022
|
Please find attached EDS reply
|
|
21
|
Nodal Officer
|
REPLY
|
State secretary
|
17/06/2022
|
Please find attached EDS reply.
|
|
22
|
State secretary
|
REPLY
|
Regional Office
|
27/07/2022
|
EDS reply
|
|
23
|
Regional Office
|
EDS
|
State secretary
|
30/08/2022
|
EDS letter dated 30.08.2022.
|
|
24
|
State secretary
|
EDS
|
Nodal Officer
|
19/09/2022
|
please eds reply
|
|
25
|
Nodal Officer
|
EDS
|
CF (Udaipur)
|
19/09/2022
|
please reply
|
|
26
|
CF (Udaipur)
|
EDS
|
DFO (Banswara Territorial)
|
20/09/2022
|
Please find attached EDS
|
|
27
|
DFO (Banswara Territorial)
|
REPLY
|
CF (Udaipur)
|
10/11/2022
|
Government of India,ministry of environment,forest & climatechange Integrated Regional Office,Jaipur letter File no.8 b/raj/12/30/2021/FC dated 30.08.2022 information letter ready and uploaded with all documents.
|
|
28
|
CF (Udaipur)
|
REPLY
|
Nodal Officer
|
17/11/2022
|
EDS reply
|
|
29
|
Nodal Officer
|
REPLY
|
State secretary
|
01/12/2022
|
Reply attached.
|
|
30
|
State secretary
|
REPLY
|
Regional Office
|
13/12/2022
|
EDS reply
|
|