A. General Details
  (i). Proposal No. : FP/RJ/OFC/50901/2020              (ii). Name of Project for which Forest Land is required : Laying of Underground Optical Fiber Cable Along the NH-21(old NH11) Road Within the Existing Row from Mahuwa to Samleti GP, NTR –T Joint to Patoli , Hadiya to Teekri Jafran NH Crosing and Hadiya T-Joint to Pali T-Joint –District-Dausa (Rajasthan)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Laying of Underground Optical Fiber Cable Along the NH-21(old NH11) Road Within the Existing Row from Mahuwa to Samleti GP, NTR –T Joint to Patoli , Hadiya to Teekri Jafran NH Crosing and Hadiya T-Joint to Pali T-Joint –District-Dausa (Rajasthan)” Total Length 4004 meter              (iv). File no. : 1(9)forest/2021              (v). State : Rajasthan              (vi). Category of the Project : Optical Fibre Cable              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.1602
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/RJ/OFC/50901/202017/10/2020aa22/10/2020   04/11/2020 Dausa Territorial :05/11/2020Jaipur:
  15/12/2020 (Dausa Territorial)

Rajasthan:
24/12/2020
Rajasthan:
04/01/2021
24/02/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Dausa Territorial) on:02/12/2020  
Replied by UA on :05/12/2020  
Query raised by DFO (Dausa Territorial) on:14/12/2020  
Replied by UA on :14/12/2020  
NOTE:- Stage-I Approval accorded by : State Government .