TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/RJ/OFC/43321/2019              (ii). Name of Project for which Forest Land is required : BHARATNET PROJECT              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : To provide Broadband connectivity in Gram Panchayats Gurdah & Badarpur of Karauali District by Govt. Of India under Flagship program of Digital India              (iv). File no. : 8B/Raj/09/17/2020/FC              (v). State : Rajasthan              (vi). Category of the Project : Optical Fibre Cable              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.5625
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/RJ/OFC/43321/201912/01/202020/01/2020   28/01/2020   30/01/2020   03/02/2020 Karauli Territorial :03/02/2020Bharatpur:
  28/02/2020 (Karauli Territorial)

Rajasthan:
04/03/2020
Rajasthan:
17/03/2020
Jaipur:
16/06/2020
21/07/2020
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Karauli Territorial) on:17/02/2020  
Replied by UA on :22/02/2020  
Query raised by DFO (Karauli Territorial) on:26/02/2020  
Replied by UA on :26/02/2020  
NOTE:- Stage-I Approval accorded by : Regional Office .