Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Sriganganagar Territorial)
|
EDS
|
User Agency (ioclfca13gb@gmail.com)
|
09/03/2022
|
while site inspection it was observed that their is difference between the location plotted on the map and the actual location of the petrol pump. Please rectify the maps.
|
|
2
|
User Agency (ioclfca13gb@gmail.com)
|
REPLY
|
DFO (Sriganganagar Territorial)
|
13/04/2022
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Bikaner)
|
04/05/2022
|
1. CA scheme has to be given for planting of 110 plants.
2. An additional copy of hard copy should be provided as the proposal has to be sanctioned by IRO jaipur.
|
|
4
|
CF (Bikaner)
|
EDS
|
DFO (Sriganganagar Territorial)
|
10/05/2022
|
1. CA scheme has to be given for planting of 110 plants. 2. An additional copy of hard copy should be provided as the proposal has to be sanctioned by IRO jaipur.
|
|
5
|
DFO (Sriganganagar Territorial)
|
EDS
|
User Agency (ioclfca13gb@gmail.com)
|
17/05/2022
|
An additional copy of hard copy should be provided as the proposal has to be sanctioned by IRO jaipur.
|
|
6
|
User Agency (ioclfca13gb@gmail.com)
|
REPLY
|
DFO (Sriganganagar Territorial)
|
01/06/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Sriganganagar Territorial)
|
REPLY
|
CF (Bikaner)
|
08/06/2022
|
ca scheme is given for 110 plants and one more copy of the project has sent
|
|
8
|
CF (Bikaner)
|
REPLY
|
Nodal Officer
|
16/06/2022
|
as per attachment.
|
|
9
|
Regional Office
|
EDS
|
State secretary
|
18/01/2023
|
EDS letter dated 18.10.2023.
|
|
10
|
State secretary
|
EDS
|
Nodal Officer
|
01/02/2023
|
please eds reply
|
|
11
|
Nodal Officer
|
EDS
|
CF (Bikaner)
|
01/02/2023
|
Kindly provide information as per attached document
|
|
12
|
CF (Bikaner)
|
EDS
|
DFO (Sriganganagar Territorial)
|
03/02/2023
|
Kindly provide information as per attached document
|
|
13
|
DFO (Sriganganagar Territorial)
|
EDS
|
User Agency (ioclfca13gb@gmail.com)
|
20/02/2023
|
Kindly provide information as per attached document
|
|
14
|
User Agency (ioclfca13gb@gmail.com)
|
REPLY
|
DFO (Sriganganagar Territorial)
|
01/06/2023
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Sriganganagar Territorial)
|
EDS
|
User Agency (ioclfca13gb@gmail.com)
|
19/06/2023
|
while site inspection it was observed that their no demarcation so, it is not possible to send updated enumeration tree list
|
|
16
|
User Agency (ioclfca13gb@gmail.com)
|
REPLY
|
DFO (Sriganganagar Territorial)
|
22/06/2023
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Sriganganagar Territorial)
|
REPLY
|
CF (Bikaner)
|
05/07/2023
|
THE CORRECTION HAS BEEN MADE
|
|
18
|
CF (Bikaner)
|
EDS
|
DFO (Sriganganagar Territorial)
|
26/07/2023
|
Kindly certify whether tree felling and alternate alignment is avoidable or not as sought by nodal higher office.
|
|
19
|
DFO (Sriganganagar Territorial)
|
EDS
|
User Agency (ioclfca13gb@gmail.com)
|
01/08/2023
|
Kindly certify whether tree felling and alternate alignment is avoidable or not as sought by nodal higher office
|
|
20
|
User Agency (ioclfca13gb@gmail.com)
|
REPLY
|
DFO (Sriganganagar Territorial)
|
14/08/2023
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Sriganganagar Territorial)
|
REPLY
|
CF (Bikaner)
|
16/08/2023
|
the report has been sent
|
|
22
|
CF (Bikaner)
|
REPLY
|
Nodal Officer
|
18/08/2023
|
as per attachment.
|
|
23
|
Nodal Officer
|
REPLY
|
State secretary
|
27/09/2023
|
Reply is attached.
|
|
24
|
State secretary
|
REPLY
|
Regional Office
|
17/11/2023
|
EDS Reply
|
|