TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/RJ/Approach/148689/2021              (ii). Name of Project for which Forest Land is required : Construction of Approach Road for Proposed Indian Oil Corporation Ltd. Retail Outlet on Bikaner-Sri Ganganagar Road (NH-62) between KM Stone No. 189 - 190 (Chainage: 189.692 to 189.727) RHS in Kila No 9 & 10 Murbba No 11, at Village - 17 STB, Tehsil-Suratgarh, District - Sri Ganganagar, Raj.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of Approach Road for Proposed Indian Oil Corporation Ltd. Retail Outlet on Bikaner-Sri Ganganagar Road (NH-62) between KM Stone No. 189 - 190 (Chainage: 189.692 to 189.727) RHS in Kila No 9 & 10 Murbba No 11, at Village - 17 STB, Tehsil-Suratgarh, District - Sri Ganganagar, Raj.              (iv). File no. : 1(105)Forest/2023              (v). State : Rajasthan              (vi). Category of the Project : Approach Access              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.1817
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/RJ/Approach/148689/202103/12/202110/12/2021   15/02/2023   15/02/2023   28/02/2023 Sriganganagar Territorial :18/04/2023Bikaner:
  12/07/2023 (Sriganganagar Territorial)

Rajasthan:
28/07/2023
Rajasthan:
06/09/2023
20/12/2023
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Sriganganagar Territorial) on:05/06/2023  
Replied by UA on :25/06/2023  
NOTE:- Stage-I Approval accorded by : State Government .
Close(X)
Close(X)