Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Mamit)
|
EDS
|
User Agency (rajeev.kumar@ircon.org)
|
15/01/2018
|
Please provide Justification of Forest Land Proposed for Diversion
|
|
2
|
User Agency (rajeev.kumar@ircon.org)
|
REPLY
|
DFO (Mamit)
|
01/02/2018
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Mamit)
|
EDS
|
User Agency (rajeev.kumar@ircon.org)
|
16/03/2018
|
As FC had been violated due to continuing encroachment and illicit construction Penal Compensatory Afforestation covering 150.46 ha. which is double of the area encraoched is required.
As per rough estimation with norms under National Afforestation Programme, the cost of Afforestation of 150.46 ha. will come to the tune of Rs 188.07 lakhs approximately
|
|
4
|
User Agency (rajeev.kumar@ircon.org)
|
REPLY
|
DFO (Mamit)
|
12/12/2019
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Mamit)
|
EDS
|
User Agency (rajeev.kumar@ircon.org)
|
24/02/2020
|
No land for Compensatory Afforestation has been given and in the mean time NIT and Higher and Technical Education department had simply started excavation of the site without taking approval from competent authority
|
|