Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Thenzawl)
|
EDS
|
User Agency (eepiupwdmz@gmail.com)
|
23/09/2019
|
CA area have not yet been intimated by the user agency till date. the need for joint inspection and verification of the proposed site have been intimated to the user agency and have been asjed to propose a convenient date, which have no yet been intimated too till date. the department is awating action form the user agency as of now.
|
|
2
|
User Agency (eepiupwdmz@gmail.com)
|
REPLY
|
DFO (Thenzawl)
|
08/07/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Thenzawl)
|
EDS
|
User Agency (eepiupwdmz@gmail.com)
|
15/12/2021
|
The CA area for diversion land for the project have not yet been transferred and mutated to Forest department and therefore UA may approach Revenue department for identification of the CA area at the earliest
|
|
4
|
User Agency (eepiupwdmz@gmail.com)
|
REPLY
|
DFO (Thenzawl)
|
03/02/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Lunglei)
|
EDS
|
User Agency (eepiupwdmz@gmail.com)
|
10/02/2022
|
Field verication submitted to NO, FCA
|
|
6
|
User Agency (eepiupwdmz@gmail.com)
|
REPLY
|
DFO (Lunglei)
|
18/04/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Thenzawl)
|
EDS
|
User Agency (eepiupwdmz@gmail.com)
|
27/04/2022
|
CA area in lieu of proposed diversion of land for the project has not yet been transferred and mutated to EF&CC Dept till today. As such Form A Part II can not be completed from DFO level due to absence of notification for CA area. The UA may approach Revenue dept for identification and notification of CA area for the project
|
|