TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KL/VELEC/23616/2017              (ii). Name of Project for which Forest Land is required : Chennagiri 8 acre under total electrification scheme              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction 1 km LT sph line through forest land for electrification of chennagiri 6 acre and 8 acre area under total electrification scheme og kerala Govt              (iv). State : Kerala              (v). Category of the Project : Village Electricity              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.12
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KL/VELEC/23616/201713/01/201714/02/2017   20/02/2017   16/01/2017   13/02/2017 Thenmala :21/02/2017Southern Circle, Kollam:
  25/03/2017 (Thenmala)

Kerala:
27/03/2017
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Kerala) on:17/07/2017  
Query raised by Circle (Southern Circle, Kollam) on:25/03/2017  
Replied by DFO (Thenmala) on:27/03/2017  
Query raised by Circle (Southern Circle, Kollam) on:22/12/2017  
Replied by DFO () on:  
NOTE:- Proposal is pending at DFO due to EDS raised by Nodal Officer .