Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (xenpmgsyudhampur@gmail.com)
|
11/08/2020
|
User Agency did not turn up for Joint verification
|
|
2
|
User Agency (xenpmgsyudhampur@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
31/10/2020
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (xenpmgsyudhampur@gmail.com)
|
03/11/2020
|
you are requested to submit original hard copies of KML & Legible copy ot Toposheet
|
|
4
|
User Agency (xenpmgsyudhampur@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
15/12/2020
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (xenpmgsyudhampur@gmail.com)
|
18/12/2020
|
Earlier the date of joint verification was fixed on 11-12-2020 but no representative turned up and the next date of joint verification fixed on 24-12-2020. Besides this the KML files as desired earlier have not been received
|
|
6
|
User Agency (xenpmgsyudhampur@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
25/01/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (xenpmgsyudhampur@gmail.com)
|
29/01/2021
|
Original hard copy of KML file, Legible copy of toposheet, Muck Disposal Plan & Cost benefit analysis required
|
|
8
|
User Agency (xenpmgsyudhampur@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
29/01/2021
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (xenpmgsyudhampur@gmail.com)
|
04/02/2021
|
Provide Brief Project note
|
|
10
|
User Agency (xenpmgsyudhampur@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
05/02/2021
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (xenpmgsyudhampur@gmail.com)
|
05/02/2021
|
Requisite Hard copies be provided
|
|
12
|
User Agency (xenpmgsyudhampur@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
08/02/2021
|
The correction have been made as per the instruction received
|
|
13
|
CF (East Circle Jammu)
|
EDS
|
DFO (Ramnagar Forest Division)
|
16/02/2021
|
Please upload the requistie information.
|
|
14
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (xenpmgsyudhampur@gmail.com)
|
16/02/2021
|
Please Upload the requisite information
|
|
15
|
User Agency (xenpmgsyudhampur@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
17/02/2021
|
The correction have been made as per the instruction received
|
|
16
|
DFO (Ramnagar Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
17/02/2021
|
As desired, the requisite documents have been uploaded
|
|
17
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
19/02/2021
|
Kindly make correction in part-I of Form-A about total period for which the forest land is proposed to be diverted
|
|
18
|
CF (East Circle Jammu)
|
EDS
|
DFO (Ramnagar Forest Division)
|
19/02/2021
|
Please make correction as required.
|
|
19
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (xenpmgsyudhampur@gmail.com)
|
19/02/2021
|
The period of the road has not been mentioned in Form-A Part X
|
|
20
|
User Agency (xenpmgsyudhampur@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
19/02/2021
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Ramnagar Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
19/02/2021
|
As desired the correction has been made
|
|
22
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
19/02/2021
|
The correction has been made as per requirement.
|
|
23
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
20/02/2021
|
Kindly upload the CA Plan
|
|
24
|
CF (East Circle Jammu)
|
EDS
|
DFO (Ramnagar Forest Division)
|
20/02/2021
|
Kindly upload the CA Plan
|
|
25
|
DFO (Ramnagar Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
20/02/2021
|
As desired, CA plan uploaded
|
|
26
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
20/02/2021
|
CA plan has been uploaded.
|
|
27
|
Regional Office
|
EDS
|
State secretary
|
26/04/2021
|
EDS
|
|
28
|
State secretary
|
EDS
|
Nodal Officer
|
28/04/2021
|
Please provide the requisite information as desired by MoEF&CC
|
|
29
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
28/04/2021
|
Kindly upload the requisite information please.
|
|
30
|
CF (East Circle Jammu)
|
EDS
|
DFO (Ramnagar Forest Division)
|
04/05/2021
|
pls do needful
|
|
31
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (xenpmgsyudhampur@gmail.com)
|
04/05/2021
|
The requisite information may kindly be uploaded / provided
|
|
32
|
User Agency (xenpmgsyudhampur@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
05/05/2021
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (xenpmgsyudhampur@gmail.com)
|
08/05/2021
|
The requisite information may kindly be uploaded and provided hard copies as well
|
|
34
|
User Agency (xenpmgsyudhampur@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
14/05/2021
|
The correction have been made as per the instruction received
|
|
35
|
DFO (Ramnagar Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
20/05/2021
|
The correction has been made as per EDS
|
|
36
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
21/05/2021
|
Corrections done
|
|
37
|
Nodal Officer
|
REPLY
|
State secretary
|
25/05/2021
|
The requisite documents have been uploaded
|
|
38
|
State secretary
|
REPLY
|
Regional Office
|
27/05/2021
|
The requisite documents in response to the observations have been uploaded by the user agency/DFORamnagar/Nodal officer
|
|
39
|
Regional Office
|
EDS
|
State secretary
|
17/06/2021
|
Proposal return back to modify errors.
|
|
40
|
State secretary
|
EDS
|
Nodal Officer
|
17/06/2021
|
Proposal return back to modify errors.
|
|
41
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
18/06/2021
|
Please modify the errors as suggested in the REC meeting
|
|
42
|
CF (East Circle Jammu)
|
EDS
|
DFO (Ramnagar Forest Division)
|
18/06/2021
|
Kindly modify the corrections as discussed in the REC meeting
|
|
43
|
DFO (Ramnagar Forest Division)
|
EDS
|
User Agency (xenpmgsyudhampur@gmail.com)
|
18/06/2021
|
Kindly modify the corrections as discussed in the REC meeting
|
|
44
|
User Agency (xenpmgsyudhampur@gmail.com)
|
REPLY
|
DFO (Ramnagar Forest Division)
|
18/06/2021
|
The correction have been made as per the instruction received
|
|
45
|
DFO (Ramnagar Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
18/06/2021
|
EDS REMOVED
|
|
46
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
18/06/2021
|
needful has been done
|
|
47
|
Nodal Officer
|
REPLY
|
State secretary
|
18/06/2021
|
The needful has been done.
|
|
48
|
State secretary
|
REPLY
|
Regional Office
|
18/06/2021
|
The needful has been done by Nodal officer (FCA).
|
|
49
|
Regional Office
|
EDS
|
State secretary
|
28/06/2021
|
EDS
|
|
50
|
State secretary
|
EDS
|
Nodal Officer
|
29/06/2021
|
EDS
|
|
51
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
29/06/2021
|
The CF/DFO/User Agency are requested to see the minutes of the REC held on 17-18/06/2021 and further upload the requisite documents /information.
|
|
52
|
CF (East Circle Jammu)
|
EDS
|
DFO (Ramnagar Forest Division)
|
30/06/2021
|
Please upload the requisite documents /information.
|
|
53
|
DFO (Ramnagar Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
02/07/2021
|
The correction has been made as per EDS
|
|
54
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
03/07/2021
|
Correction has been made as per EDS by concerned DFO and U/A.
|
|
55
|
Nodal Officer
|
REPLY
|
State secretary
|
05/07/2021
|
The necessary correction has been made.
|
|
56
|
State secretary
|
REPLY
|
Regional Office
|
06/07/2021
|
The necessary correction has been made by Nodal Officer (FCA).
|
|