Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Batote Forest Division)
|
EDS
|
User Agency (xenramban-pmgsy@jk.gov.in)
|
12/09/2022
|
Huge no of conifer trees are involved, so please explore some alternative available along the proposed alignment besides information with regard to total length of the proposed road along with length constructed and remaining length to be constructed in the instant proposal
|
|
2
|
User Agency (xenramban-pmgsy@jk.gov.in)
|
REPLY
|
DFO (Batote Forest Division)
|
15/09/2022
|
The correction have been made as per the instruction received
|
|
3
|
State secretary
|
EDS
|
Nodal Officer
|
01/11/2022
|
The Proposal has been recommended for rejection by DFO Batote. In this regard you are requested to kindly convey whether the User agency has been informed of the decision.
|
|
4
|
Nodal Officer
|
REPLY
|
State secretary
|
10/11/2022
|
The requisite information has been uploaded.
|
|
5
|
State secretary
|
EDS
|
Nodal Officer
|
05/07/2023
|
EDS
|
|
6
|
Nodal Officer
|
EDS
|
CF (Chenab Circle Doda)
|
14/07/2023
|
for further necessary action
|
|
7
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Batote Forest Division)
|
22/07/2023
|
Kindly upload the requisite information please.
|
|
8
|
DFO (Batote Forest Division)
|
EDS
|
User Agency (xenrambanpmgsy@gmail.com)
|
17/08/2023
|
please upload copy of AA as per pdf uploaded.
|
|
9
|
User Agency (xenrambanpmgsy@gmail.com)
|
REPLY
|
DFO (Batote Forest Division)
|
04/09/2023
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Batote Forest Division)
|
EDS
|
User Agency (xenrambanpmgsy@gmail.com)
|
23/11/2023
|
Please upload the requisite document regarding AA as desired as per attached pdf.
|
|
11
|
User Agency (xenrambanpmgsy@gmail.com)
|
REPLY
|
DFO (Batote Forest Division)
|
07/05/2024
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Batote Forest Division)
|
REPLY
|
CF (Chenab Circle Doda)
|
30/05/2024
|
The desired document regarding AA of the project stands uploaded by the user agency in Part-A. Hence submitted for considerations.
|
|
13
|
CF (Chenab Circle Doda)
|
REPLY
|
Nodal Officer
|
08/06/2024
|
The desired document regarding AA of the project stands uploaded by the user agency in Part-A. Hence submitted for considerations.
|
|
14
|
Nodal Officer
|
REPLY
|
State secretary
|
08/07/2024
|
The requisite document has been uploaded by user agency
|
|
15
|
State secretary
|
EDS
|
Nodal Officer
|
16/07/2024
|
To clarify whether any AA exists/has been issued for the fresh proposal uploaded by UA as the project in question has been sanctioned for the existing project for which forest land already stands diverted and whether if in the negative, can the case be processed
|
|
16
|
Nodal Officer
|
EDS
|
CF (Chenab Circle Doda)
|
22/07/2024
|
To clarify whether any AA exists/has been issued for the fresh proposal uploaded by UA as the project in question has been sanctioned for the existing project for which forest land already stands diverted and whether if in the negative, can the case be processed
|
|
17
|
CF (Chenab Circle Doda)
|
EDS
|
DFO (Batote Forest Division)
|
26/07/2024
|
To clarify whether any AA exists/has been issued for the fresh proposal uploaded by UA as the project in question has been sanctioned for the existing project for which forest land already stands diverted and whether if in the negative, can the case be processed
|
|
18
|
DFO (Batote Forest Division)
|
EDS
|
User Agency (xenrambanpmgsy@gmail.com)
|
24/10/2024
|
To clarify whether any AA exists/has been issued for the fresh proposal uploaded by UA as the project in question has been sanctioned for the existing project for which forest land already stands diverted and whether if in the negative, can the case be processed
|
|
19
|
User Agency (xenrambanpmgsy@gmail.com)
|
REPLY
|
DFO (Batote Forest Division)
|
29/11/2024
|
The correction have been made as per the instruction received
|
|
20
|
DFO (Batote Forest Division)
|
EDS
|
User Agency (xenrambanpmgsy@gmail.com)
|
01/02/2025
|
It is advised that the consent letter to withdraw the case may be uploaded at the withdraw option given on Parivesh.
|
|