Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
22/01/2021
|
Signature in the Joint Inspection Report Pending
|
|
2
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
26/01/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
11/02/2021
|
The information is urgently required for further processing of the case. 1. Minimum use of forest land.
2. Certificate of CA not as per prescribed format.
3. Certificate of NPV not as er prescribed format.
|
|
4
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
15/02/2021
|
The correction have been made as per the instruction received
|
|
5
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Mahore Forest Division)
|
17/02/2021
|
Kindly provide cost benefit analysis and muck disposal plan
|
|
6
|
DFO (Mahore Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
17/02/2021
|
sir the cost benefit analysis report, muck disposal plan and NPV calculation sheet has been uploaded
|
|
7
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
18/02/2021
|
Kindly upload the requisite information please.
|
|
8
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Mahore Forest Division)
|
18/02/2021
|
Kindly upload the requisite information please.
|
|
9
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
19/02/2021
|
Eds raised as area involved in dumping sites is more than the Forest area involved in the road alignment
|
|
10
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
26/02/2021
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Mahore Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
26/02/2021
|
the justification certificate has been uploaded by the user agency for consideration please.
|
|
12
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
04/03/2021
|
Necessary corrections have been made by user agency and DFO
|
|
13
|
State secretary
|
EDS
|
Nodal Officer
|
01/04/2021
|
Pl upload the requisite documents EDS attaced
|
|
14
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
06/04/2021
|
Kindly upload the requisite information please.
|
|
15
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Mahore Forest Division)
|
06/04/2021
|
Please upload the requisite documents
|
|
16
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
06/04/2021
|
kindly provide AA and FRA certificate for this project please.
|
|
17
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
07/04/2021
|
The correction have been made as per the instruction received
|
|
18
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
08/04/2021
|
make necessary corrections please
|
|
19
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
08/04/2021
|
The correction have been made as per the instruction received
|
|
20
|
DFO (Mahore Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
08/04/2021
|
Sir Administrative approval of the project and FRA certificate uploaded by the user agency. Joint Inspection Report and Clarification for not selecting non forest land submitted by DFO Office by your ready reference sir please.
|
|
21
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
10/04/2021
|
The requisite documents have been uploaded
|
|
22
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
12/04/2021
|
Kindly upload the requisite information please.
|
|
23
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Mahore Forest Division)
|
12/04/2021
|
Kindly upload the requisite information please.
|
|
24
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
12/04/2021
|
sir please upload muck disposal plan and DGPS map of the project site
|
|
25
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
18/04/2021
|
The correction have been made as per the instruction received
|
|
26
|
DFO (Mahore Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
19/04/2021
|
Sir the necessary correction has been made both the model CA plan and Muck disposal plan has been uploaded by the user agency and DFO office.
|
|
27
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
19/04/2021
|
The requisite documents have been uploaded
|
|
28
|
Nodal Officer
|
REPLY
|
State secretary
|
19/04/2021
|
The requisite information has been uploaded.
|
|
29
|
State secretary
|
EDS
|
Nodal Officer
|
18/05/2021
|
Pls provide addl document
|
|
30
|
Nodal Officer
|
REPLY
|
State secretary
|
18/05/2021
|
The information has been uploaded.
|
|
31
|
State secretary
|
EDS
|
Nodal Officer
|
18/05/2021
|
Pls upload
|
|
32
|
Nodal Officer
|
REPLY
|
State secretary
|
18/05/2021
|
The requisite information has been replied
|
|
33
|
Regional Office
|
EDS
|
State secretary
|
02/06/2021
|
EDS
|
|
34
|
State secretary
|
EDS
|
Nodal Officer
|
04/06/2021
|
EDS
|
|
35
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
05/06/2021
|
Please upload the requisite documents
|
|
36
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Mahore Forest Division)
|
07/06/2021
|
Please upload the requisite documents
|
|
37
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
08/06/2021
|
please upload the requisite documents
|
|
38
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
10/06/2021
|
The correction have been made as per the instruction received
|
|
39
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
10/06/2021
|
Please do the necessary correction
|
|
40
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
10/06/2021
|
The correction have been made as per the instruction received
|
|
41
|
DFO (Mahore Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
10/06/2021
|
Sir all the necessary corrections has been done by the user agency. Also undertaking to pay additional NPV certificate has been uploaded and site specific CA Plan approved by the Conservator Sir. Hence recommended for further processing please.
|
|
42
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
10/06/2021
|
Requisite documents have been uploaded
|
|
43
|
Nodal Officer
|
REPLY
|
State secretary
|
11/06/2021
|
The requisite documents have been uploaded
|
|
44
|
State secretary
|
REPLY
|
Regional Office
|
11/06/2021
|
The requisite documents have been uploaded
|
|
45
|
Regional Office
|
EDS
|
State secretary
|
28/06/2021
|
EDS
|
|
46
|
State secretary
|
EDS
|
Nodal Officer
|
29/06/2021
|
EDS
|
|
47
|
Nodal Officer
|
EDS
|
CF (West Circle Rajouri)
|
29/06/2021
|
The CF/DFO/User Agency are requested to see the minutes of the REC meeting held on 17 & 18/06-2021 and further upload the requisite information/documents.
|
|
48
|
CF (West Circle Rajouri)
|
EDS
|
DFO (Mahore Forest Division)
|
30/06/2021
|
Please do the needful
|
|
49
|
DFO (Mahore Forest Division)
|
EDS
|
User Agency (xenpmgsymahore121@gmail.com)
|
30/06/2021
|
Please do the necessary corrections
|
|
50
|
User Agency (xenpmgsymahore121@gmail.com)
|
REPLY
|
DFO (Mahore Forest Division)
|
05/07/2021
|
The correction have been made as per the instruction received
|
|
51
|
DFO (Mahore Forest Division)
|
REPLY
|
CF (West Circle Rajouri)
|
06/07/2021
|
sir all the formalities have been completed by the user agency and this office has also uploaded the revised enumeration list for kind perusal please. hence submitted for favor of information sir please.
|
|
52
|
CF (West Circle Rajouri)
|
REPLY
|
Nodal Officer
|
07/07/2021
|
sir
the EDS raised in minutes of the REC meeting held on 17 & 18/06-2021 , the user agency has uploaded the document. hence submitted for kind perusal
|
|
53
|
Nodal Officer
|
REPLY
|
State secretary
|
08/07/2021
|
The requisite documents have been uploaded by user agency and DFO Mahore
|
|
54
|
State secretary
|
REPLY
|
Regional Office
|
08/07/2021
|
The requisite documents have been uploaded by user agency and DFO Mahore
|
|