  (i). Proposal No. : FP/HR/TRANS/40398/2019              (ii). Name of Project for which Forest Land is required : 66 kV Double Circuit line form 220 kV Sub Station Raiwali to 66 kV Sub Station HSIIDC (IE) Barwala              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : For Construction of 66 KV D/C Line From 220 KV S/Stn Raiwali to 66 KV S/ Stn Hsiidc Barwala crossing various strips of Protected forest land, under Forest Division & Distt. Panchkula              (iv). State : Haryana              (v). Category of the Project : Transmission Line              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.2016
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/TRANS/40398/201924/05/201929/05/2019   30/05/2019   30/05/2019   24/06/2019 Panchkula :25/06/2019
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Proposal is pending at DFO .