  (i). Proposal No. : FP/HR/OFC/156628/2022              (ii). Name of Project for which Forest Land is required : LAYING OF UNDERGROUND OFC BY JIO DIGITAL FIBRE PVT LTD IN SONIPAT DIVISION              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : LAYING OF UNDERGROUND OFC BY JIO DIGITAL FIBRE PRIVATE LID IN FOREST DIVISION SONIPAT. TOTAL ROUTE LENGHT WOULD BE REQUIRED 0.0495 HECTARE (1100 METERS). (SA KNLI 0106)              (iv). State : Haryana              (v). Category of the Project : Optical Fibre Cable              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.0495
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/OFC/156628/202209/06/2022aa18/07/2022   16/11/2022 Sonipat :06/12/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Sonipat) on:11/01/2023  
Replied by UA on :07/06/2023  
Query raised by DFO (Sonipat) on:12/07/2023  
Replied by UA on :24/08/2023  
Query raised by DFO (Sonipat) on:14/09/2023  
Replied by UA on :15/09/2023  
Query raised by DFO (Sonipat) on:10/10/2023  
Replied by UA on :18/05/2024  
Query raised by DFO (Sonipat) on:03/07/2024  
Replied by UA on :06/07/2024  
Query raised by DFO (Sonipat) on:20/08/2024  
Replied by UA on :13/09/2024  
NOTE:- Proposal is pending at DFO .