TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/Approach/154002/2022              (ii). Name of Project for which Forest Land is required : : Const. of approach access from Nizampur Nangal Chaudhary road to Bayal road for Shree Ram Stone Crusher Panchnota district Mahendergarh              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : : Const. of approach access from Nizampur Nangal Chaudhary road to Bayal road for Shree Ram Stone Crusher Panchnota district Mahendergarh. The project approved by HSPCB Panchkula for CTE vide ltr no. 313129218MAHCTE6117016 dated 26.12.2018              (iv). State : Haryana              (v). Category of the Project : Approach Access              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.0098
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/Approach/154002/202201/04/202210/05/2022   10/05/2022   13/05/2022   26/05/2022 Mahendergarh :02/06/2022South Circle Gurgaon:
  22/08/2022 (Mahendergarh)

Haryana:
29/11/2022
Haryana:
08/05/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Haryana) on:09/05/2023  
Replied by Nodal Officer (Haryana) on:01/06/2023  
Query raised by State Government (Haryana) on:12/06/2023  
Replied by Nodal Officer (Haryana) on:16/06/2023  
Query raised by State Government (Haryana) on:23/06/2023  
Replied by Nodal Officer (Haryana) on:23/06/2023  
Query raised by State Government (Haryana) on:17/07/2023  
Replied by Nodal Officer (Haryana) on:12/09/2023  
Query raised by State Government (Haryana) on:20/10/2023  
Replied by Nodal Officer (Haryana) on:21/02/2024  
Query raised by State Government (Haryana) on:19/04/2024  
Query raised by Nodal Officer (Haryana) on:18/01/2023  
Replied by Circle(South Circle Gurgaon) on:25/01/2023  
Query raised by Nodal Officer (Haryana) on:27/01/2023  
Replied by Circle(South Circle Gurgaon) on:03/02/2023  
Query raised by Nodal Officer (Haryana) on:09/05/2023  
Replied by Circle(South Circle Gurgaon) on:23/05/2023  
Query raised by Nodal Officer (Haryana) on:18/07/2023  
Replied by Circle(South Circle Gurgaon) on:25/08/2023  
Query raised by Nodal Officer (Haryana) on:20/10/2023  
Replied by Circle(South Circle Gurgaon) on:19/01/2024  
Query raised by Nodal Officer (Haryana) on:23/04/2024  
Replied by Circle() on:  
Query raised by Circle (South Circle Gurgaon) on:30/08/2022  
Replied by DFO (Mahendergarh) on:14/11/2022  
Query raised by Circle (South Circle Gurgaon) on:19/01/2023  
Replied by DFO (Mahendergarh) on:24/01/2023  
Query raised by Circle (South Circle Gurgaon) on:27/01/2023  
Replied by DFO (Mahendergarh) on:02/02/2023  
Query raised by Circle (South Circle Gurgaon) on:10/05/2023  
Replied by DFO (Mahendergarh) on:19/05/2023  
Query raised by Circle (South Circle Gurgaon) on:21/07/2023  
Replied by DFO (Mahendergarh) on:23/08/2023  
Query raised by Circle (South Circle Gurgaon) on:26/10/2023  
Replied by DFO (Mahendergarh) on:19/01/2024  
Query raised by Circle (South Circle Gurgaon) on:23/04/2024  
Replied by DFO () on:  
Query raised by DFO (Mahendergarh) on:07/09/2022  
Replied by UA on :04/11/2022  
Query raised by DFO (Mahendergarh) on:29/04/2024  
Replied by UA on :  
NOTE:- Proposal is pending at DELISTED (due to non-reply of EDS by UA within 90 days) due to EDS raised by DELISTED .