Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Palwal)
|
EDS
|
User Agency (bharatpetroleum.office@gmail.com)
|
19/07/2022
|
please find attached letter
|
|
2
|
User Agency (bharatpetroleum.office@gmail.com)
|
REPLY
|
DFO (Palwal)
|
01/09/2022
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
23/02/2023
|
EDS
|
|
4
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Mewat)
|
24/02/2023
|
letter attached
|
|
5
|
DFO (Mewat)
|
REPLY
|
CF (South Circle Gurgaon)
|
15/09/2023
|
Report attached
|
|
6
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
19/09/2023
|
EDS replied.
|
|
7
|
State secretary
|
EDS
|
Nodal Officer
|
04/12/2023
|
1. Upload Toposheet of Diverted land with number and Countersigned by User Agency
2. Upload Coloured DGPS map of Diverted land
3. Upload Justification letter in part I
4. Revise all checklists with signed by Neeraj K Jarria
5. Upload copy of CLU Letter in Part I
6. What are the SMC Charges to be taken According to the letter no FCA 3467 dated 09.03.2023 of the Pccf Office What Scheme may the SMC Charges not be taken
7.Revise CA scheme with new rate of CA and ACA
|
|
8
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
04/12/2023
|
1. Upload Toposheet of Diverted land with number and Countersigned by User Agency 2. Upload Coloured DGPS map of Diverted land 3. Upload Justification letter in part I 4. Revise all checklists with signed by Neeraj K Jarria 5. Upload copy of CLU Letter in Part I 6. What are the SMC Charges to be taken According to the letter no FCA 3467 dated 09.03.2023 of the Pccf Office What Scheme may the SMC Charges not be taken 7.Revise CA scheme with new rate of CA and ACA
|
|
9
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Mewat)
|
06/12/2023
|
1. Upload Toposheet of Diverted land with number and Countersigned by User Agency 2. Upload Coloured DGPS map of Diverted land 3. Upload Justification letter in part I 4. Revise all checklists with signed by Neeraj K Jarria 5. Upload copy of CLU Letter in Part I 6. What are the SMC Charges to be taken According to the letter no FCA 3467 dated 09.03.2023 of the Pccf Office What Scheme may the SMC Charges not be taken 7.Revise CA scheme with new rate of CA and ACA
|
|
10
|
DFO (Mewat)
|
EDS
|
User Agency (bharatpetroleum.office@gmail.com)
|
28/12/2023
|
1. Upload Toposheet of Diverted land with number and Countersigned by User Agency 2. Upload Coloured DGPS map of Diverted land 3. Upload Justification letter in part I 4. Revise all checklists with signed by Neeraj K Jarria 5. Upload copy of CLU Letter in Part I 6. What are the SMC Charges to be taken According to the letter no FCA 3467 dated 09.03.2023 of the Pccf Office What Scheme may the SMC Charges not be taken 7.Revise CA scheme with new rate of CA and ACA
|
|
11
|
User Agency (bharatpetroleum.office@gmail.com)
|
REPLY
|
DFO (Mewat)
|
28/12/2023
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Mewat)
|
EDS
|
User Agency (bharatpetroleum.office@gmail.com)
|
05/02/2024
|
1. Upload Toposheet of Diverted land with number and Countersigned by User Agency 2. Upload Coloured DGPS map of Diverted land 3. Upload Justification letter in part I 4. Revise all checklists with signed by Neeraj K Jarria 5. Upload copy of CLU Letter in Part I
|
|
13
|
User Agency (bharatpetroleum.office@gmail.com)
|
REPLY
|
DFO (Mewat)
|
26/03/2024
|
The correction have been made as per the instruction received
|
|
14
|
DFO (Mewat)
|
REPLY
|
CF (South Circle Gurgaon)
|
28/03/2024
|
letter
|
|
15
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
28/03/2024
|
EDS Replied by DFO
|
|
16
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
02/04/2024
|
Justification uploaded in Part-1, S.No. 3 other proposal, needs to be uploaded correct document.
|
|
17
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Mewat)
|
03/04/2024
|
Justification uploaded in Part-1, S.No. 3 other proposal, needs to be uploaded correct document.
|
|
18
|
DFO (Mewat)
|
EDS
|
User Agency (bharatpetroleum.office@gmail.com)
|
08/04/2024
|
Justification uploaded in Part-1, S.No. 3 other proposal, needs to be uploaded correct document.
|
|
19
|
User Agency (bharatpetroleum.office@gmail.com)
|
REPLY
|
DFO (Mewat)
|
09/04/2024
|
The correction have been made as per the instruction received
|
|
20
|
DFO (Mewat)
|
REPLY
|
CF (South Circle Gurgaon)
|
09/04/2024
|
Uploaded the check list 10 (Justification)
|
|
21
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
09/04/2024
|
EDS replied by DFO
|
|
22
|
Nodal Officer
|
REPLY
|
State secretary
|
02/05/2024
|
The correction have been made as per the instruction received
|
|
23
|
State secretary
|
EDS
|
Nodal Officer
|
20/05/2024
|
Resubmit after formulation of revised CA Scheme by concerned DFO Giving certification on parameter such as 1. Site suitability and availability for recommended CA site 2. total plants which can be planted on the site Recommended 3. No of proposals of plants along with proposal no which has been recommended against the part CA site which is recommended 4. Details of Plantation under the existing Proposal.
|
|
24
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
22/05/2024
|
Resubmit after formulation of revised CA Scheme by concerned DFO Giving certification on parameter such as 1. Site suitability and availability for recommended CA site 2. total plants which can be planted on the site Recommended 3. No of proposals of plants along with proposal no which has been recommended against the part CA site which is recommended 4. Details of Plantation under the existing Proposal.
|
|
25
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Mewat)
|
23/05/2024
|
Resubmit after formulation of revised CA Scheme by concerned DFO Giving certification on parameter such as 1. Site suitability and availability for recommended CA site 2. total plants which can be planted on the site Recommended 3. No of proposals of plants along with proposal no which has been recommended against the part CA site which is recommended 4. Details of Plantation under the existing Proposal.
|
|
26
|
DFO (Mewat)
|
REPLY
|
CF (South Circle Gurgaon)
|
14/06/2024
|
Forwarding
|
|
27
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
18/06/2024
|
EDS replied.
|
|
28
|
Nodal Officer
|
REPLY
|
State secretary
|
24/07/2024
|
ED
|
|