Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Gurgaon)
|
EDS
|
User Agency (ioclbasai@gmail.com)
|
24/02/2022
|
Detail attached
|
|
2
|
User Agency (ioclbasai@gmail.com)
|
REPLY
|
DFO (Gurgaon)
|
17/03/2022
|
The correction have been made as per the instruction received
|
|
3
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Gurgaon)
|
01/06/2022
|
Letter attached.
|
|
4
|
DFO (Gurgaon)
|
EDS
|
User Agency (ioclbasai@gmail.com)
|
06/06/2022
|
Detail Attached
|
|
5
|
User Agency (ioclbasai@gmail.com)
|
REPLY
|
DFO (Gurgaon)
|
06/06/2022
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Gurgaon)
|
REPLY
|
CF (South Circle Gurgaon)
|
10/06/2022
|
In ref to your office letter no.948 dt.31.05.2022
|
|
7
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Gurgaon)
|
16/06/2022
|
Letter attached.
|
|
8
|
DFO (Gurgaon)
|
EDS
|
User Agency (ioclbasai@gmail.com)
|
21/06/2022
|
detail attached
|
|
9
|
User Agency (ioclbasai@gmail.com)
|
REPLY
|
DFO (Gurgaon)
|
22/06/2022
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Gurgaon)
|
REPLY
|
CF (South Circle Gurgaon)
|
24/06/2022
|
in ref to your office letter 1149 dated 16.06.2022
|
|
11
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
05/08/2022
|
Case Down
|
|
12
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Gurgaon)
|
08/08/2022
|
Letter Attached.
|
|
13
|
DFO (Gurgaon)
|
REPLY
|
CF (South Circle Gurgaon)
|
08/09/2022
|
In ref to PCCF letter no. E/1459-60 dt. 05-08-2022
|
|
14
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
12/09/2022
|
Query replied
|
|
15
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
13/09/2022
|
Upload correct and clear CA Scheme in part II column no 13 Addl information
|
|
16
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Gurgaon)
|
13/09/2022
|
Upload correct and clear CA Scheme in part II column no 13 Addl information
|
|
17
|
DFO (Gurgaon)
|
REPLY
|
CF (South Circle Gurgaon)
|
15/09/2022
|
the correction has been made as per instruction. Clear CA Scheme uploaded
|
|
18
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
20/09/2022
|
the correction has been made as per instruction. Clear CA Scheme uploaded by DFO.
|
|
19
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
09/12/2022
|
1.in coloumn 13 i of part II plantation area is wrong 0.09252 ha instead of 0.185ha
2.Marking list is not uploaded
3.name of documents is not given in addl information details
4.Toposheet of CA site is without number
|
|
20
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Gurgaon)
|
09/12/2022
|
1.in coloumn 13 i of part II plantation area is wrong 0.09252 ha instead of 0.185ha 2.Marking list is not uploaded 3.name of documents is not given in addl information details 4.Toposheet of CA site is without number
|
|
21
|
DFO (Gurgaon)
|
REPLY
|
CF (South Circle Gurgaon)
|
13/12/2022
|
the correction has been made as per instruction received
|
|
22
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Gurgaon)
|
13/12/2022
|
Pl check and upload documents.
|
|
23
|
DFO (Gurgaon)
|
REPLY
|
CF (South Circle Gurgaon)
|
13/12/2022
|
the correction has been done
|
|
24
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
14/12/2022
|
EDS Replied.
|
|
25
|
State secretary
|
EDS
|
Nodal Officer
|
15/02/2023
|
The forest area falls in ECO sensitive zone .
|
|
26
|
Nodal Officer
|
REPLY
|
State secretary
|
27/10/2023
|
EDS Reply
|
|
27
|
State secretary
|
EDS
|
Nodal Officer
|
11/01/2024
|
Proposal return to Nodal office due to area is less than 0.1 ha
|
|
28
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
08/02/2024
|
letter attached
|
|
29
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Gurgaon)
|
08/02/2024
|
case down
|
|
30
|
DFO (Gurgaon)
|
REPLY
|
CF (South Circle Gurgaon)
|
14/03/2024
|
In ref of MoEF&CC letter no.9-HRB182/2023-CHA dt. 19.12.2023
|
|
31
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
19/03/2024
|
EDS Replied
|
|
32
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
05/04/2024
|
Case down
|
|
33
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Gurgaon)
|
08/04/2024
|
Letter attached.
|
|
34
|
DFO (Gurgaon)
|
REPLY
|
CF (South Circle Gurgaon)
|
18/06/2024
|
In ref to APCCF, Panchkula letter No.D-III-10520/14 dt. 04-04-2024
|
|
35
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
20/06/2024
|
EDS replied
|
|
36
|
Nodal Officer
|
REPLY
|
State secretary
|
01/08/2024
|
Stage I Granted
|
|