Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Regional Office
|
EDS
|
State secretary
|
08/06/2022
|
EDS
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
10/06/2022
|
forward to DFO for upload the information
|
|
3
|
Nodal Officer
|
EDS
|
CF (Central Circle Rohtak)
|
10/06/2022
|
forward to DFO for upload the information
|
|
4
|
CF (Central Circle Rohtak)
|
EDS
|
DFO (Sonipat)
|
10/06/2022
|
Query
|
|
5
|
DFO (Sonipat)
|
EDS
|
User Agency (arihantpolymersnoc@gmail.com)
|
16/06/2022
|
Essential not completed
|
|
6
|
User Agency (arihantpolymersnoc@gmail.com)
|
REPLY
|
DFO (Sonipat)
|
28/06/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Sonipat)
|
EDS
|
User Agency (arihantpolymersnoc@gmail.com)
|
29/06/2022
|
Essential not completed
|
|
8
|
User Agency (arihantpolymersnoc@gmail.com)
|
REPLY
|
DFO (Sonipat)
|
23/08/2022
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Sonipat)
|
EDS
|
User Agency (arihantpolymersnoc@gmail.com)
|
13/09/2022
|
Essential not completed
|
|
10
|
User Agency (arihantpolymersnoc@gmail.com)
|
REPLY
|
DFO (Sonipat)
|
19/09/2022
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Sonipat)
|
REPLY
|
CF (Central Circle Rohtak)
|
19/10/2022
|
Essential completed
|
|
12
|
CF (Central Circle Rohtak)
|
REPLY
|
Nodal Officer
|
21/10/2022
|
Query Remove
|
|
13
|
Nodal Officer
|
EDS
|
CF (Central Circle Rohtak)
|
27/12/2022
|
Case down
|
|
14
|
CF (Central Circle Rohtak)
|
EDS
|
DFO (Sonipat)
|
28/12/2022
|
Query
|
|
15
|
DFO (Sonipat)
|
EDS
|
User Agency (arihantpolymersnoc@gmail.com)
|
05/01/2023
|
Essential not completed
|
|
16
|
User Agency (arihantpolymersnoc@gmail.com)
|
REPLY
|
DFO (Sonipat)
|
17/04/2023
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Sonipat)
|
REPLY
|
CF (Central Circle Rohtak)
|
21/06/2023
|
Essential completed
|
|
18
|
CF (Central Circle Rohtak)
|
REPLY
|
Nodal Officer
|
21/06/2023
|
Query Remove
|
|
19
|
Nodal Officer
|
EDS
|
CF (Central Circle Rohtak)
|
03/08/2023
|
1. Layout plant is without countersigned by DFO.
2. CA scheme is uploaded without Cost norms.
3. NPV calculation is wrong as density of area 0.4, hence needs to be corrected.
4. DGPS Map revise as per the changed KML.
|
|
20
|
CF (Central Circle Rohtak)
|
EDS
|
DFO (Sonipat)
|
04/08/2023
|
1. Layout plant is without countersigned by DFO. 2. CA scheme is uploaded without Cost norms. 3. NPV calculation is wrong as density of area 0.4, hence needs to be corrected. 4. DGPS Map revise as per the changed KML.
|
|
21
|
DFO (Sonipat)
|
EDS
|
User Agency (arihantpolymersnoc@gmail.com)
|
08/09/2023
|
Essential not completed
|
|
22
|
User Agency (arihantpolymersnoc@gmail.com)
|
REPLY
|
DFO (Sonipat)
|
24/11/2023
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Sonipat)
|
REPLY
|
CF (Central Circle Rohtak)
|
01/04/2024
|
Essential has been completed
|
|
24
|
CF (Central Circle Rohtak)
|
REPLY
|
Nodal Officer
|
02/04/2024
|
Query Remove
|
|
25
|
Nodal Officer
|
EDS
|
CF (Central Circle Rohtak)
|
09/04/2024
|
1. Layout plan is without countersigned by DFO. 2. Kml file of CA site INCORRECT The KML file covers parts of drain, which is not correct. Please revise the KML to include only the area proposed for plantation. 3. DGPS Map of CA site INCORRECT It needs to be revised as per the KML file.
|
|
26
|
CF (Central Circle Rohtak)
|
EDS
|
DFO (Sonipat)
|
09/04/2024
|
1. Layout plan is without countersigned by DFO. 2. Kml file of CA site INCORRECT The KML file covers parts of drain, which is not correct. Please revise the KML to include only the area proposed for plantation. 3. DGPS Map of CA site INCORRECT It needs to be revised as per the KML file.
|
|
27
|
DFO (Sonipat)
|
EDS
|
User Agency (arihantpolymersnoc@gmail.com)
|
26/04/2024
|
Essential not completed
|
|
28
|
User Agency (arihantpolymersnoc@gmail.com)
|
REPLY
|
DFO (Sonipat)
|
14/05/2024
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Sonipat)
|
REPLY
|
CF (Central Circle Rohtak)
|
03/07/2024
|
Essential completed
|
|
30
|
CF (Central Circle Rohtak)
|
EDS
|
DFO (Sonipat)
|
03/07/2024
|
Please upload - 1. Layout plan is without countersigned by DFO. 2. Kml file of CA site INCORRECT The KML file covers parts of drain, which is not correct. Please revise the KML to include only the area proposed for plantation. 3. DGPS Map of CA site INCORRECT It needs to be revised as per the KML file.
|
|
31
|
DFO (Sonipat)
|
EDS
|
User Agency (arihantpolymersnoc@gmail.com)
|
03/07/2024
|
Provide the approved Layout plan hard in Sonipat forest division
|
|