Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
02/08/2021
|
forward to DFO, Fatehabad
|
|
2
|
CF (West Circle Hissar)
|
EDS
|
DFO (Fatehabad)
|
03/08/2021
|
forward to DFO, Fatehabad
|
|
3
|
DFO (Fatehabad)
|
EDS
|
User Agency (jindalsteelmajra@gmail.com)
|
13/10/2021
|
Provide NOC of Pollution Control Board.
|
|
4
|
User Agency (jindalsteelmajra@gmail.com)
|
REPLY
|
DFO (Fatehabad)
|
26/07/2023
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Fatehabad)
|
REPLY
|
CF (West Circle Hissar)
|
28/07/2023
|
EDS removed forwarding letter & Undertaking given by User agency attached.
|
|
6
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
02/08/2023
|
EDS removed forwarding letter & Undertaking given by User agency attached.
|
|
7
|
State secretary
|
EDS
|
Nodal Officer
|
19/09/2023
|
1. Upload clear copy of Diverted toposheet with sign by user agency
2. upload DGPS map of Diverted site with signed by User Agency
3.Upload clear copy of DTP noc in part I
4. Upload clear and coloured toposhhet of CA site with number of sheet
5. in part II coloumn no 4 density of vegition shows as 0.2 but inn recommended letter by DFO its shows as nil pls revise the recommended letter with correction of density of vegitation
|
|
8
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
19/09/2023
|
1. Upload clear copy of Diverted toposheet with sign by user agency 2. upload DGPS map of Diverted site with signed by User Agency 3.Upload clear copy of DTP NOC in part I 4. Upload clear and colored toposheet of CA site with number of sheet 5. in part II column no 4 density of vegetation shows as 0.2 but inn recommended letter by DFO its shows as nil pls revise the recommended letter with correction of density of vegetation.
|
|
9
|
CF (West Circle Hissar)
|
EDS
|
DFO (Fatehabad)
|
20/09/2023
|
1. Upload clear copy of Diverted toposheet with sign by user agency 2. upload DGPS map of Diverted site with signed by User Agency 3.Upload clear copy of DTP NOC in part I 4. Upload clear and colored toposheet of CA site with number of sheet 5. in part II column no 4 density of vegetation shows as 0.2 but inn recommended letter by DFO its shows as nil pls revise the recommended letter with correction of density of vegetation.
|
|
10
|
DFO (Fatehabad)
|
EDS
|
User Agency (jindalsteelmajra@gmail.com)
|
22/09/2023
|
EDS raised. Remove Objection letter attached. 1. Upload clear copy of Diverted toposheet with sign by user agency 2. upload DGPS map of Diverted site with signed by User Agency 3.Upload clear copy of DTP NOC in part I
|
|
11
|
User Agency (jindalsteelmajra@gmail.com)
|
REPLY
|
DFO (Fatehabad)
|
03/11/2023
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Fatehabad)
|
REPLY
|
CF (West Circle Hissar)
|
03/11/2023
|
All objection removed by user agency and division level letter attached.
|
|
13
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
06/11/2023
|
All objection removed by user agency and division level letter attached.
|
|
14
|
Nodal Officer
|
REPLY
|
State secretary
|
21/11/2023
|
EDS Reply
|
|
15
|
State secretary
|
EDS
|
Nodal Officer
|
11/01/2024
|
Proposal return to Nodal office due to area is less than 0.1 ha
|
|
16
|
Nodal Officer
|
REPLY
|
State secretary
|
09/02/2024
|
W.r.t. your online query dated.11/01/2024, It is intimated that since there is no provision to process such type of proposals at DCF/CCF level in Parivesh 1.0 for Stage-I & II Approval. Therefore proposal is forwarded to you for further action.
|
|
17
|
State secretary
|
EDS
|
Nodal Officer
|
19/04/2024
|
1. Toposheet of Project site is blurry and without sign by User Agency Pls revise toposheet and re upload in part I coloumn C iv
2. Uploaded DGPS map of Project site is without sign. PLs upload DGPS map with sign and stamp by user agency
|
|
18
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
23/04/2024
|
1. Toposheet of Project site is blurry and without sign by User Agency Pls revise toposheet and re upload in part I column C iv 2. Uploaded DGPS map of Project site is without sign. PLs upload DGPS map with sign and stamp by user agency.
|
|
19
|
CF (West Circle Hissar)
|
EDS
|
DFO (Fatehabad)
|
23/04/2024
|
1. Toposheet of Project site is blurry and without sign by User Agency Pls revise toposheet and re upload in part I column C iv 2. Uploaded DGPS map of Project site is without sign. PLs upload DGPS map with sign and stamp by user agency.
|
|
20
|
DFO (Fatehabad)
|
EDS
|
User Agency (jindalsteelmajra@gmail.com)
|
29/04/2024
|
1. Toposheet of Project site is blurry and without sign by User Agency Pls revise toposheet and re upload in part I column C iv 2. Uploaded DGPS map of Project site is without sign. PLs upload DGPS map with sign and stamp by user agency
|
|
21
|
User Agency (jindalsteelmajra@gmail.com)
|
REPLY
|
DFO (Fatehabad)
|
02/05/2024
|
The correction have been made as per the instruction received
|
|
22
|
DFO (Fatehabad)
|
REPLY
|
CF (West Circle Hissar)
|
03/05/2024
|
Survey sheet and diverted land DGPS map uploaded in part 1 with user agency sign and stamp.
|
|
23
|
CF (West Circle Hissar)
|
REPLY
|
Nodal Officer
|
03/05/2024
|
Survey sheet and diverted land DGPS map uploaded in part 1 with user agency sign and stamp.
|
|
24
|
Nodal Officer
|
EDS
|
CF (West Circle Hissar)
|
16/10/2024
|
Case down
|
|
25
|
CF (West Circle Hissar)
|
EDS
|
DFO (Fatehabad)
|
18/10/2024
|
Case down
|
|
26
|
DFO (Fatehabad)
|
EDS
|
User Agency (jindalsteelmajra@gmail.com)
|
20/11/2024
|
Please Remove objection 1 to 9 and 11 for necessary action.
|
|