Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Kaithal)
|
EDS
|
User Agency (sahab04111979@gmail.com)
|
13/05/2021
|
Please submit NOC of PWD B&R department for further necessary action.
|
|
2
|
User Agency (sahab04111979@gmail.com)
|
REPLY
|
DFO (Kaithal)
|
27/01/2022
|
The correction have been made as per the instruction received
|
|
3
|
CF (North Circle Panchkula)
|
EDS
|
DFO (Kaithal)
|
16/03/2022
|
send the report as attachment
|
|
4
|
DFO (Kaithal)
|
EDS
|
User Agency (sahab04111979@gmail.com)
|
22/03/2022
|
send the report as attachment
|
|
5
|
User Agency (sahab04111979@gmail.com)
|
REPLY
|
DFO (Kaithal)
|
30/05/2022
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Kaithal)
|
REPLY
|
CF (North Circle Panchkula)
|
02/06/2022
|
R/Ssir, The correction have been made as per the instruction received
|
|
7
|
Nodal Officer
|
EDS
|
CF (North Circle Panchkula)
|
09/08/2022
|
Case Down
|
|
8
|
CF (North Circle Panchkula)
|
EDS
|
DFO (Kaithal)
|
10/08/2022
|
please updated information
|
|
9
|
DFO (Kaithal)
|
EDS
|
User Agency (sahab04111979@gmail.com)
|
12/08/2022
|
sir, please remove the objection as per letter attached at sr. no. 4,5,6,7 related to user agency
|
|
10
|
User Agency (sahab04111979@gmail.com)
|
REPLY
|
DFO (Kaithal)
|
12/09/2022
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Kaithal)
|
REPLY
|
CF (North Circle Panchkula)
|
19/12/2022
|
The correction have been made as per the instruction received
|
|
12
|
CF (North Circle Panchkula)
|
REPLY
|
Nodal Officer
|
20/12/2022
|
The correction have been made by DFO
|
|
13
|
Nodal Officer
|
EDS
|
CF (North Circle Panchkula)
|
21/02/2023
|
EDS
|
|
14
|
CF (North Circle Panchkula)
|
EDS
|
DFO (Kaithal)
|
23/02/2023
|
please update case according the instruction
|
|
15
|
DFO (Kaithal)
|
REPLY
|
CF (North Circle Panchkula)
|
01/05/2023
|
OBJECTION REMOVED AS PER DIRECTION OF NODAL OFFICE
|
|
16
|
CF (North Circle Panchkula)
|
REPLY
|
Nodal Officer
|
05/05/2023
|
objection removed by dfo
|
|
17
|
Nodal Officer
|
EDS
|
CF (North Circle Panchkula)
|
09/06/2023
|
1. Upload toposheet of CA site with toposheet No. 2. Upload toposheet of project site with No. and signature of the competent authority.
|
|
18
|
CF (North Circle Panchkula)
|
EDS
|
DFO (Kaithal)
|
12/06/2023
|
Upload toposheet of CA site with toposheet No. 2. Upload toposheet of project site with No. and signature of the competent authority.
|
|
19
|
DFO (Kaithal)
|
EDS
|
User Agency (sahab04111979@gmail.com)
|
15/06/2023
|
Please Upload toposheet/Survey Sheet of India of project site with Sr. No. with Stamp/signature of User agency Head.
|
|
20
|
User Agency (sahab04111979@gmail.com)
|
REPLY
|
DFO (Kaithal)
|
13/07/2023
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Kaithal)
|
REPLY
|
CF (North Circle Panchkula)
|
14/07/2023
|
R/Sir
EDS has been removed as per Online objection.
|
|
22
|
CF (North Circle Panchkula)
|
REPLY
|
Nodal Officer
|
20/07/2023
|
report updated by dfo
|
|
23
|
Nodal Officer
|
EDS
|
CF (North Circle Panchkula)
|
22/08/2023
|
Upload revised CA scheme as per latest cost norms dated 15.05.2023
|
|
24
|
CF (North Circle Panchkula)
|
EDS
|
DFO (Kaithal)
|
29/08/2023
|
Upload revised CA scheme as per latest cost norms dated 15.05.2023
|
|
25
|
DFO (Kaithal)
|
REPLY
|
CF (North Circle Panchkula)
|
04/09/2023
|
R/Sir
EDS removed as per online remarks.
|
|
26
|
CF (North Circle Panchkula)
|
REPLY
|
Nodal Officer
|
05/09/2023
|
DFO Kaithal has uploaded revised CA Scheme
|
|
27
|
State secretary
|
EDS
|
Nodal Officer
|
21/09/2023
|
in part II column no 15 site Inspection report by DFO the user agency has violated the prevision of Forest act 1980but in RECOMMENDED LETTER BY DFO MAY VOILATION BE NIL FILLED . PLS UPLOAD REVISE PART II LETTER .
2. UPLOAD VOILATION REPORT
3.In this case, the user agency has committed a violation and In PCCF Recommended letter may not have written the violation. Revise the recommended letter and upload in part II coloumn no 16
|
|
28
|
Nodal Officer
|
EDS
|
CF (North Circle Panchkula)
|
21/09/2023
|
In part II column no 15 site Inspection report by DFO the user agency has violated the prevision of Forest act 1980but in RECOMMENDED LETTER BY DFO MAY VOILATION BE NIL FILLED . PLS UPLOAD REVISE PART II LETTER. 2. UPLOAD VOILATION REPORT 3. In this case, the user agency has committed a violation and In PCCF Recommended letter may not have written the violation. Revise the recommended letter and upload in part II column no 16
|
|
29
|
CF (North Circle Panchkula)
|
EDS
|
DFO (Kaithal)
|
05/10/2023
|
revised the case according to the given instructions
|
|
30
|
DFO (Kaithal)
|
REPLY
|
CF (North Circle Panchkula)
|
12/10/2023
|
R/Sir
EDS removed in compliance of your online remarks and revised site inspection report uploaded.
|
|
31
|
CF (North Circle Panchkula)
|
REPLY
|
Nodal Officer
|
17/10/2023
|
case updated by DFO
|
|
32
|
Nodal Officer
|
REPLY
|
State secretary
|
19/10/2023
|
Site inspection report has been uploaded after making correction.
|
|
33
|
State secretary
|
EDS
|
Nodal Officer
|
01/05/2024
|
1. Uploaded Toposheet of Proposed Site is without Signature
2. Uploaded DGPS map of Proposed Site is without Signature
3. Density of Vegitation is not match with the part II
|
|
34
|
Nodal Officer
|
EDS
|
CF (North Circle Panchkula)
|
01/05/2024
|
1. Uploaded Toposheet of Proposed Site is without Signature 2. Uploaded DGPS map of Proposed Site is without Signature 3. Density of Vegetation is not match with the part II
|
|
35
|
CF (North Circle Panchkula)
|
EDS
|
DFO (Kaithal)
|
06/05/2024
|
1. Uploaded Toposheet of Proposed Site is without Signature 2. Uploaded DGPS map of Proposed Site is without Signature 3. Density of Vegetation is not match with the part II
|
|
36
|
DFO (Kaithal)
|
EDS
|
User Agency (sahab04111979@gmail.com)
|
14/05/2024
|
1.Uploaded Toposheet of Proposed Site is without Signature 2. Uploaded DGPS map of Proposed Site is without Signature.
|
|
37
|
User Agency (sahab04111979@gmail.com)
|
REPLY
|
DFO (Kaithal)
|
14/05/2024
|
The correction have been made as per the instruction received
|
|
38
|
DFO (Kaithal)
|
REPLY
|
CF (North Circle Panchkula)
|
14/05/2024
|
EDS removed as per instructions received :
1) Toposheet of proposed site is uploaded by UA with signature.
2) DGPS map with signature has been uploaded by UA.
3) Density of Vegetation Recommendation has been changed in Part 2 but column16.3 has been locked due to which it cannot be uploaded in Column No. 16.3, it has been uploaded in Additional information. Kindly process the case.
|
|
39
|
CF (North Circle Panchkula)
|
REPLY
|
Nodal Officer
|
28/05/2024
|
case updated by DFO
|
|
40
|
Nodal Officer
|
EDS
|
CF (North Circle Panchkula)
|
13/09/2024
|
EDS by Nodal Office
|
|
41
|
CF (North Circle Panchkula)
|
EDS
|
DFO (Kaithal)
|
16/09/2024
|
forwarded case
|
|