  (i). Proposal No. : FP/DN/VELEC/30058/2017              (ii). Name of Project for which Forest Land is required : Erection of 100KVA Transformer center with HT line at village Sindoni-Loharmal              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Erection of 100KVA Transformer center with HT line at village Sindoni-Loharmal              (iv). File no. : DN-027/2017              (v). State : Dadar & Nagar Haveli              (vi). Category of the Project : Village Electricity              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.91
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/DN/VELEC/30058/201707/11/201709/11/2017   20/12/2017   26/12/2017   05/01/2018 Territorial Division :05/01/2018Forest Department, Dadra & Nagar Haveli, Silvassa.:
  14/06/2018 (Territorial Division)

Dadar & Nagar Haveli:
19/06/2018
Dadar & Nagar Haveli:
28/06/2018
26/07/2018
By :State Government
08/08/2024
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Territorial Division) on:10/01/2018  
Replied by UA on :27/01/2018  
Query raised by DFO (Territorial Division) on:08/02/2018  
Replied by UA on :28/02/2018  
NOTE:- Stage-II Approval accorded by : State Government .