Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Territorial Division)
|
EDS
|
User Agency (ee-road-dnh@nic.in)
|
10/12/2018
|
Please find enclosed herewith the Letter.
|
|
2
|
User Agency (ee-road-dnh@nic.in)
|
REPLY
|
DFO (Territorial Division)
|
18/06/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Territorial Division)
|
EDS
|
User Agency (ee-road-dnh@nic.in)
|
20/07/2021
|
Please find enclosed herewith letter
|
|
4
|
User Agency (ee-road-dnh@nic.in)
|
REPLY
|
DFO (Territorial Division)
|
24/11/2021
|
The correction have been made as per the instruction received
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
22/07/2022
|
EDS letter dated 22.07.2022.
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
04/08/2022
|
Please Comply the letter
|
|
7
|
Nodal Officer
|
EDS
|
CF (Forest Department, Dadra & Nagar Haveli, Silvassa.)
|
04/08/2022
|
Please Comply
|
|
8
|
CF (Forest Department, Dadra & Nagar Haveli, Silvassa.)
|
EDS
|
DFO (Territorial Division)
|
04/08/2022
|
Please Comply
|
|
9
|
DFO (Territorial Division)
|
EDS
|
User Agency (ee-road-dnh@nic.in)
|
05/08/2022
|
Please Comply
|
|
10
|
User Agency (ee-road-dnh@nic.in)
|
REPLY
|
DFO (Territorial Division)
|
16/09/2022
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Territorial Division)
|
REPLY
|
CF (Forest Department, Dadra & Nagar Haveli, Silvassa.)
|
19/09/2022
|
Compliance have been uploaded
|
|
12
|
CF (Forest Department, Dadra & Nagar Haveli, Silvassa.)
|
REPLY
|
Nodal Officer
|
19/09/2022
|
Compliance uploaded submitted for approval please.
|
|
13
|
Nodal Officer
|
REPLY
|
State secretary
|
19/09/2022
|
Compliance have been submitted for kind approval and signature please
|
|
14
|
State secretary
|
REPLY
|
Regional Office
|
19/09/2022
|
Submitted for kind approval please
|
|
15
|
Regional Office
|
EDS
|
State secretary
|
29/09/2022
|
Please upload the complete reply of this office EDS letter dated 22.07.2022.
|
|
16
|
State secretary
|
REPLY
|
Regional Office
|
29/09/2022
|
1. Documents re-submitted
2. KML includes existing road hence area shown is greater. Actual area for diversion is 17.82 ha only.
|
|