TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/DN/Others/149878/2021              (ii). Name of Project for which Forest Land is required : Bhilosa Private Limited Pipeline              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.4098 Hect. Protected Forest land (Road Parallel land) for laying 8” dia (20 cm) NaturalGas Pipeline from our existing pipeline near village Naroli, Taluka Silvassa, Dist. Valsad to Bhilosa Private Limited in Dadra and Nagar Haveli              (iv). File no. : 7-2/3-FD/653              (v). State : Dadar & Nagar Haveli              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.4098
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/DN/Others/149878/202104/12/2021aa13/12/2021   04/01/2022 Territorial Division :25/05/2022Forest Department, Dadra & Nagar Haveli, Silvassa.:
  26/05/2022 (Territorial Division)

Dadar & Nagar Haveli:
26/05/2022
Dadar & Nagar Haveli:
26/05/2022
31/05/2022
By :State Government
07/11/2023
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-II Approval accorded by : State Government .
Close(X)
Close(X)
Please wait ...