A. General Details
  (i). Proposal No. : FP/UP/WATER/47013/2020              (ii). Name of Project for which Forest Land is required : Protected Forest Land Proposed to be Diverted for Laying of Drinking Water Pipeline along Jhansi-Bhagwantpura Road from Ch.1.00 to 4.00 Tehsil:Jhansi Under Jhansi Water Supply Reorganization Sechme Phase-1, in District: Jhansi              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Laying of Drinking Water Pipeline along Jhansi-Bhagwantpura Road from Ch.1.00 to 4.00 Tehsil:Jhansi Under Jhansi Water Supply Reorganization Sechme Phase-1, in District: Jhansi              (iv). File no. : 2698/81-2-2020-800(122)/2020              (v). State : Uttar Pradesh              (vi). Category of the Project : Drinking Water              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.4
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/UP/WATER/47013/202002/07/202031/08/2020  03/07/2020   17/09/2020  07/07/2020   07/07/2020   27/08/2020 Forest Division Jhansi :17/09/2020Bundelkhand Circle Jhansi:
  06/10/2020 (Forest Division Jhansi)

Uttar Pradesh:
09/10/2020
Uttar Pradesh:
12/11/2020
16/02/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Uttar Pradesh) on:23/11/2020  
Replied by Nodal Officer (Uttar Pradesh) on:22/12/2020  
Query raised by Nodal Officer (Uttar Pradesh) on:12/10/2020  
Replied by Circle(Bundelkhand Circle Jhansi) on:10/11/2020  
Query raised by Nodal Officer (Uttar Pradesh) on:23/11/2020  
Replied by Circle(Bundelkhand Circle Jhansi) on:18/12/2020  
Query raised by Circle (Bundelkhand Circle Jhansi) on:15/10/2020  
Replied by DFO (Forest Division Jhansi) on:10/11/2020  
Query raised by Circle (Bundelkhand Circle Jhansi) on:10/12/2020  
Replied by DFO (Forest Division Jhansi) on:18/12/2020  
Query raised by DFO (Forest Division Jhansi) on:23/10/2020  
Replied by UA on :09/11/2020  
Query raised by DFO (Forest Division Jhansi) on:10/12/2020  
Replied by UA on :11/12/2020  
NOTE:- Stage-I Approval accorded by : State Government .